AI insight
No early warning on this project
Only a 41% chance of a further slip on current trends.
Apply NDMO policies and build a single master-data register.
Budget (BAC)
Actual cost
65% of budget
Progress
Planned 70%
Estimate at completion
SAR +1.1M
SPI · CPI
Forecast finish
18 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control20 October 2026
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
80
Solid
Index over the last six reports
May to October 2026
No material change in the health dimensions over the period.
AI insight
Only a 41% chance of a further slip on current trends.
Generated from the live project data
The project is behind plan: 62% done against 70% planned.
SPI 0.89, CPI 0.95.
3 of 5 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 76% of budget
0 approvals and 0 open actions on this project
1 open risk, exposure SAR 650K
Impact
0 escalated
2 of 4 approved
4 members