PRJ-2026-016At risk7ExecutionWaterfall

Data Governance & Master Data Management

Add to watchlist

Apply NDMO policies and build a single master-data register.

Budget (BAC)

SAR 21.5M

Actual cost

SAR 14M

⁦65%⁩ of budget

Progress

⁦62%⁩

Planned ⁦70%⁩

Estimate at completion

SAR 22.6M

SAR +1.1M

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control20 October 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate14 February 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate29 August 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate13 September 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate20 October 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−9

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is behind plan: ⁦62%⁩ done against ⁦70%⁩ planned.

SPI ⁦0.89⁩, CPI ⁦0.95⁩.

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦76%⁩ of budget

14M/ 21.5M1.1Mprojected overrun(⁦5.3%⁩)
Actual spend
14M
Committed
16.4M
Approved budget
21.5M
Estimate at completion
22.6M

Next milestones

  • Provisional acceptance⁦2026-12-04⁩was ⁦2026-11-20⁩At risk
  • Closure⁦2027-01-18⁩was ⁦2026-12-31⁩At risk

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & issues

1 open risk, exposure SAR 650K

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0037Too few accredited data owners in the departmentsProbability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium1
  • Low0

Open issues

⁦0⁩ escalated

  • No open issues

Deliverables

⁦2⁩ of ⁦4⁩ approved

  • Project management planDLV-016-1 · V1Rahaf I. Al-Nefaie⁦2025-08-24⁩2025-08-241 Rabiʻ I 1447 AHApproved
  • Main deliverable — stage 1DLV-016-2 · V1Faisal A. Al-Shehri⁦2026-04-23⁩2026-04-236 Dhuʻl-Qiʻdah 1447 AHApproved
  • Main deliverable — final stageDLV-016-3 · V1Faisal A. Al-Shehri8 days overdue2026-10-209 Jumada I 1448 AHIn review
  • Final reportDLV-016-4 · V1Faisal A. Al-ShehriIn 64 days2026-12-3122 Rajab 1448 AHIn progress

Team, contracts & documents

Team

4 members

Rahaf I. Al-Nefaie · Director, Data & AIEng. Majed S. Al-Rasheed · VP, Digital Transformation & TechnologyRakan F. Al-Mohammadi · Data Engineer
  • Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIProject managerP-027r.alnefaie@alwaha.gov.sa⁦45%⁩
  • Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVP, Digital Transformation & TechnologyProject sponsorP-011m.alrasheed@alwaha.gov.sa⁦10%⁩
  • Rakan F. Al-MohammadiRakan F. Al-MohammadiData EngineerMaster-data modelP-032r.almohammadi@alwaha.gov.sa⁦40%⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close