Late data cataloguing delays AI model training
PRK-02-1·Mitigate·Rahaf I. Al-Nefaie
Programme · PG-02 · Digital Transformation Portfolio
Master-data governance and an analytics platform that runs AI use cases.
incl. SAR 2.5M programme reserve
28% of budget
Estimate at completion
Planned 31%
Cost performance index 0.98
Manager
Rahaf I. Al-Nefaie
Director, Data & AI
Sponsor
Eng. Majed S. Al-Rasheed
VP, Digital Transformation & Technology
Projects
2 projects
2025-08-03 — 2027-12-31
On track 1At risk 1
What the programme must achieve, and the strategic objectives it serves.
Document 60% of master data in an approved data catalogue
Put 8 AI use cases into operation by the end of 2027
One trusted source for beneficiary and asset data
Serves strategic objectives
From baseline to target
Master data documented
by 2027AI use cases in production
by 2027One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
Critical
The analytics platform needs documented, clean master data
Risks that hit more than one project, managed at programme level.
Late data cataloguing delays AI model training
PRK-02-1·Mitigate·Rahaf I. Al-Nefaie
1 risk
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 0 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 0 · Medium | 0 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 1 · Medium | 0 · Medium | 0 · High |
| 2 | 0 · Low | 0 · Low | 0 · Low | 0 · Medium | 0 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Master data documented in the data catalogue
41%
+3
Target 60%68%
AI use cases in production
6count
+1
Target 875%
Power against interest; click a person to see their role.
Keep satisfied0
Manage closely3
Monitor0
Keep informed1
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Committees
Monthly · Quorum 5
Members
6 members
Fortnightly · Quorum 4
Members
7 members
The programme’s performance is computed from these projects (§6).
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| Data Governance & Master Data ManagementPRJ-2026-016 | Rahaf I. Al-Nefaie | 7Execution | At risk | 62% | 21.5M | 22.6M+5.3% | 0.89Schedule performance index · 0.89 | 0.95Cost performance index · 0.95 |
| Analytics & AI PlatformPRJ-2026-023 | Rahaf I. Al-Nefaie | 3Initiation | On track | 1% | 28M | 28M0.0% | 1.00Schedule performance index · 1.00 | 1.00Cost performance index · 1.00 |
| Total · 2 | 49.5M | 50.6M |
SAR 49.5M
Budget
| Category | Value | Share |
|---|---|---|
| Data Governance & Master Data Management | SAR 21.5M | 43% |
| Analytics & AI Platform | SAR 28M | 57% |
| Total | SAR 49.5M | 100% |