Judicial Data Governance & Master Data
Add to watchlistApply NDMO policies and build one master register of cases and parties.
Budget (BAC)
Actual cost
65% of budget
Progress
Planned 70%
Estimate at completion
SAR +1.1M
SPI · CPI
Forecast finish
18 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control20 October 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate14 February 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate29 August 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate13 September 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate24 October 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate20 October 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-11-26 | 2026-01-28 | +63 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieHead, AI & Emerging Technologies OfficeP-027r.alnefaie@bog.gov.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-02-23 | 2026-06-13 | +110 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieHead, AI & Emerging Technologies OfficeP-027r.alnefaie@bog.gov.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-07-06 | 2026-11-13 | +130 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieHead, AI & Emerging Technologies OfficeP-027r.alnefaie@bog.gov.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-10-03 | 2026-12-15 | +73 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieHead, AI & Emerging Technologies OfficeP-027r.alnefaie@bog.gov.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-12-31 | 2027-01-16 | +16 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieHead, AI & Emerging Technologies OfficeP-027r.alnefaie@bog.gov.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline016-D1 | Approved | Rahaf I. Al-NefaieRahaf I. Al-NefaieHead, AI & Emerging Technologies OfficeP-027r.alnefaie@bog.gov.sa | Faisal A. Al-Shehri | 2025-10-13 | V1 | 2 of 2 |
| Deliverable: Monitoring & reporting016-D2 | Approved | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector, Digital Judicial Services Centre & Digital Justice Portfolio ManagerP-003f.alshehri@bog.gov.sa | Faisal A. Al-Shehri | 2025-11-26 | V1 | 2 of 2 |
| Deliverable: Business requirements016-D3 | Approved | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector, Digital Judicial Services Centre & Digital Justice Portfolio ManagerP-003f.alshehri@bog.gov.sa | Faisal A. Al-Shehri | 2026-01-10 | V1 | 2 of 2 |
| Deliverable: Solution design016-D4 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.sa | Faisal A. Al-Shehri | 2026-02-23 | V1 | 2 of 2 |
| Deliverable: Release 1016-D5 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.sa | Faisal A. Al-Shehri | 2026-04-09 | V1 | 2 of 2 |
| Deliverable: Release 2016-D6 | Approved | Rahaf I. Al-NefaieRahaf I. Al-NefaieHead, AI & Emerging Technologies OfficeP-027r.alnefaie@bog.gov.sa | Faisal A. Al-Shehri | 2026-05-23 | V1 | 2 of 2 |