PRJ-2026-016At risk7ExecutionWaterfall

Judicial Data Governance & Master Data

Add to watchlist

Apply NDMO policies and build one master register of cases and parties.

Budget (BAC)

SAR 21.5M

Actual cost

SAR 14M

⁦65%⁩ of budget

Progress

⁦62%⁩

Planned ⁦70%⁩

Estimate at completion

SAR 22.6M

SAR +1.1M

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control20 October 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate14 February 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate29 August 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate13 September 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate20 October 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2026-12-31⁩
    Budget
    SAR 21.5M
    ⁦16⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2025-08-03⁩ · by Eng. Majed S. Al-Rasheed

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2027-01-16⁩
    ⁦+16⁩ days
    Budget
    SAR 21.5M
    ⁦16⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Rahaf I. Al-Nefaie

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2026-12-31⁩⁦2027-01-16⁩

⁦+16⁩ days

Budget

SAR 21.5MSAR 21.5M

⁦0.00⁩ SAR M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2026-012026-072027-01
  • Project plan approved⁦+63⁩
  • Designs approved⁦+110⁩
  • Build complete⁦+130⁩
  • Testing & acceptance complete⁦+73⁩
  • Final handover⁦+16⁩

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦+0.14⁩
  • 2Analysis & design⁦+0.31⁩
  • 3Build⁦+0.46⁩
  • 4Testing & acceptance⁦+0.56⁩
  • 5Launch & handover⁦+0.42⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Rahaf I. Al-Nefaie
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2025-08-03⁩by Eng. Majed S. Al-Rasheed