Judicial Data Governance & Master Data
Add to watchlistApply NDMO policies and build one master register of cases and parties.
Budget (BAC)
Actual cost
65% of budget
Progress
Planned 70%
Estimate at completion
SAR +1.1M
SPI · CPI
Forecast finish
18 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control20 October 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate14 February 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate29 August 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate13 September 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate24 October 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate20 October 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started