Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-016At risk7ExecutionWaterfall

Judicial Data Governance & Master Data

Add to watchlist

Apply NDMO policies and build one master register of cases and parties.

Budget (BAC)

SAR 21.5M

Actual cost

SAR 14M

⁦65%⁩ of budget

Progress

⁦62%⁩

Planned ⁦70%⁩

Estimate at completion

SAR 22.6M

SAR +1.1M

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control20 October 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate14 February 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate29 August 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate13 September 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate20 October 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Board of Grievances

Project charter

Judicial Data Governance & Master Data

APPROVEDV2Approved ⁦2025-08-01⁩

1Project identity

Project name
Judicial Data Governance & Master Data
Project code
PRJ-2026-016
Sponsor
Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.sa
Project manager
Rahaf I. Al-NefaieRahaf I. Al-NefaieHead, AI & Emerging Technologies OfficeP-027r.alnefaie@bog.gov.sa
Business owner
Faisal A. Al-ShehriFaisal A. Al-ShehriDirector, Digital Judicial Services Centre & Digital Justice Portfolio ManagerP-003f.alshehri@bog.gov.sa
Portfolio & programme
Digital Justice PortfolioJudicial Data & AI Programme
Type & methodology
Digital · Waterfall
Current phase
7Execution

2Background & rationale

Apply NDMO policies and build one master register of cases and parties.

3Objectives

  1. 1Put emerging technology and AI to work
Serves the strategic objectives:SO-3.3Put emerging technology and AI to work

4Scope

In scope

  • Apply NDMO policies and build one master register of cases and parties.
  • Single sign-on through Nafath
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

  1. 1Single sign-on through Nafath
  2. 2Integration with internal systems
  3. 3Digital Government Authority standards

6Deliverables

1Project management plan⁦2025-08-24⁩
2Main deliverable — stage 1⁦2026-04-23⁩
3Main deliverable — final stage⁦2026-10-20⁩
4Final report⁦2026-12-31⁩

7Key milestones

  1. Charter approved⁦2025-08-01⁩
  2. Contract signed⁦2025-10-24⁩
  3. 50% of works complete⁦2026-04-23⁩
  4. Provisional acceptance⁦2026-11-20⁩
  5. Closure⁦2026-12-31⁩

8Budget

  • Main contract⁦72.1%⁩15.5M
  • Supervision & consulting⁦14.0%⁩3M
  • Internal team⁦8.8%⁩1.9M
  • Contingency reserve (⁦5%⁩)⁦5.1%⁩1.1M
The owning sector’s approved budgetTotal21.5M

9Timeline

Start
2025-08-039 Safar 1447 AH
Baseline finish
2026-12-3122 Rajab 1448 AH
Duration
⁦17⁩ months

10Key risks

  • MediumToo few accredited data owners in the courts and departments

11Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

  • Named internal staff available throughout
  • Approvals land within workflow SLAs

13Stakeholders

  • Project sponsorDecisions and funding
  • Business ownerAccepts deliverables, owns benefits
  • Projects Follow-up Office (EPMO)Governance and compliance

14Success criteria

  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • EPMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, issues, weekly statusWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Board
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close