AI insight
Smart Infrastructure Telecom Co. is a dependable partner
Strongest on Safety, weakest on Schedule adherence. It holds SAR 207.5M of live contracts with steady performance — a candidate for upcoming framework agreements.
Telecom & networks — Category A
Entity average 77
of 3 contracts on 3 projects
Paid across all its contracts: SAR 134.1M
of 1 logged
Time extension only
The seven axes the vendor is rated on each quarter, and its index across all its projects against the entity average.
Latest evaluation: Q3 2026 · 2026-10-05
| Category | Smart Infrastructure Telecom Co. | Entity average |
|---|---|---|
| Quality | 76 | 80 |
| Delivery | 70 | 74 |
| Schedule adherence | 63 | 70 |
| Compliance | 79 | 81 |
| Safety | 81 | 85 |
| Responsiveness | 68 | 74 |
| Financial standing | 74 | 75 |
Change since the Q2 2026 evaluation
Contractor performance index across its projects
Eight quarters, against the entity average and the target
AI insight
Strongest on Safety, weakest on Schedule adherence. It holds SAR 207.5M of live contracts with steady performance — a candidate for upcoming framework agreements.
Every contract of the vendor with its own performance and its project’s health — the index is built from these.
WRDA/2025/002In progress
Supply & install smart lighting and control system
Smart Street LightingAt risk
Performance
WRDA/2025/012In progress
Network & server equipment — backup data centre
National Backup Data CentreAt risk
Performance
WRDA/2025/020In progress
Fibre network roll-out — government buildings
Fibre Optic Network ExpansionAt risk
Performance
Logged: 1 · open: 0
Excavation without a permit near a gas line
SafetyCritical2026-07-28WRDA/2025/020
Vendor risks, contractual risks on its projects, and its open claims
Imported control units arriving late
Medium · Eng. Waleed O. Al-Juhani
45-day extension — customs clearance of control units
Extension of time · Submitted
Registration and compliance documents with their expiry, contact details and the evaluation history.
All documents valid
| Document | Number | Expiry | |
|---|---|---|---|
| Commercial registration | 4030316572 | 2027-04-15Expires in 169 days | |
| VAT registration certificate | 340303165720003 | 2028-12-31Expires in 795 days | |
| Zakat certificate | ZK-2026-41339 | 2027-04-30Expires in 184 days | |
| GOSI certificate | GS-882931 | 2027-01-31Expires in 95 days | |
| Nitaqat (Saudisation) certificate | NT-52183 | 2027-03-31Expires in 154 days | |
| Chamber of Commerce membership | CC-310633 | 2027-06-30Expires in 245 days | |
| Contractor classification | MC-7451 | 2027-08-31Expires in 307 days | |
| ISO 9001 certificate | ISO9001-21167 | 2027-11-30Expires in 398 days |
Quarterly evaluation by the project manager or finance
Q3 2026
2026-10-05 · Eng. Ibrahim A. Al-Ghamdi
Q2 2026
2026-07-01 · Eng. Ibrahim A. Al-Ghamdi
Q1 2026
2026-04-01 · Eng. Ibrahim A. Al-Ghamdi
Q4 2025
2026-01-01 · Eng. Ibrahim A. Al-Ghamdi
Edit: Eng. Ibrahim A. Al-Ghamdi evaluated the vendor for Q3 2026
2026-10-05 10:00Issue: Eng. Ibrahim A. Al-Ghamdi logged a violation Excavation without a permit near a gas line
2026-07-28 09:00Edit: Eng. Ibrahim A. Al-Ghamdi evaluated the vendor for Q2 2026
2026-07-01 10:00Edit: Eng. Ibrahim A. Al-Ghamdi evaluated the vendor for Q1 2026
2026-04-01 10:00