PRJ-2026-034At risk7ExecutionConstruction

Arar Administrative Courts Complex

Add to watchlist

A complex for the Northern Borders administrative court on land allocated by the municipality, with utilities and access roads.

Early warning: ⁦55%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 238M

Actual cost

SAR 81.8M

⁦34%⁩ of budget

Progress

⁦33%⁩

Planned ⁦37%⁩

Estimate at completion

SAR 247.9M

SAR +9.9M

SPI · CPI

0.89Schedule performance index · 0.890.96Cost performance index · 0.96

Forecast finish

⁦2027-09-28⁩

28 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control13 May 2027

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate17 January 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate14 August 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate7 September 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate9 November 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate13 May 2027Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started