Arar Administrative Courts Complex
Add to watchlistA complex for the Northern Borders administrative court on land allocated by the municipality, with utilities and access roads.
Budget (BAC)
Actual cost
34% of budget
Progress
Planned 37%
Estimate at completion
SAR +9.9M
SPI · CPI
Forecast finish
28 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control13 May 2027
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate17 January 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate14 August 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate7 September 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate9 November 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate13 May 2027Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+27 days vs approved
- Critical activities
- 8
- of 10 open activities
- Late activities
- 7
- past their baseline finish
- Schedule performance
- 0.49
- earned ÷ planned value
- Next milestone
- in 124 days
- Build complete
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
23 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 10 open activities, data date 2026-10-28
“Structure” needs a pace 9.3× faster than it has kept
It earned 18% in 167 days; the forecast assumes the rest in 82 days. At the pace so far it finishes on 2028-11-27.
Milestones slip 99 days on average — and it is getting worse
Each milestone’s slip in days, in date order; the later ones slip more than the early ones.
The critical chain
In date order, to final acceptance