AI insight
No early warning on this project
Only a 35% chance of a further slip on current trends.
Automated correspondence and e-archiving, linked to the government communications network.
Budget (BAC)
Actual cost
95% of budget
Progress
Planned 100%
Estimate at completion
SPI · CPI
Forecast finish
46 days behind baseline
HandoverPhase 9 of 11
Next gate:Closure30 September 2026
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
84
Solid
Index over the last six reports
May to October 2026
No material change in the health dimensions over the period.
AI insight
Only a 35% chance of a further slip on current trends.
Generated from the live project data
The project is close to plan: 95% done against 100% planned.
SPI 0.95, CPI 1.00.
4 of 5 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 98% of budget
0 approvals and 0 open actions on this project
From «My actions» for this project
0 open
Cost and schedule impact
1 open risk, exposure SAR 480K
Impact
3 of 4 approved
1 member