Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-017At risk9HandoverWaterfall

Administrative Correspondence & e-Archive Platform

Add to watchlist

Automated correspondence and e-archiving, linked to the government communications network.

Budget (BAC)

SAR 14.2M

Actual cost

SAR 13.5M

⁦95%⁩ of budget

Progress

⁦95%⁩

Planned ⁦100%⁩

Estimate at completion

SAR 14.2M

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

HandoverPhase ⁦9⁩ of ⁦11⁩

Next gate:Closure30 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate2 August 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate19 February 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate10 March 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate28 April 2025Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate5 July 2026Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate11 August 2026Handover · Current phaseHandover · Current phase
  10. Gate into «Closure»DecisionNot held yetDate30 September 2026Closure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Board of Grievances

Project charter

Administrative Correspondence & e-Archive Platform

APPROVEDV2Approved ⁦2025-01-17⁩

1Project identity

Project name
Administrative Correspondence & e-Archive Platform
Project code
PRJ-2026-017
Sponsor
Sarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.sa
Project manager
Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa
Business owner
Munirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Financial AffairsP-018m.alkhalidi@bog.gov.sa
Portfolio & programme
Technology & Enterprise Systems PortfolioEnterprise Systems & Archiving Programme
Type & methodology
IT · Waterfall
Current phase
9Handover

2Background & rationale

Automated correspondence and e-archiving, linked to the government communications network.

3Objectives

  1. 1Develop the organisational and information environment
  2. 2Improve financial planning and diversify revenue

4Scope

In scope

  • Automated correspondence and e-archiving, linked to the government communications network.
  • Migration from legacy systems
  • ERP integration

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

  1. 1Migration from legacy systems
  2. 2ERP integration
  3. 3Essential cybersecurity controls

6Deliverables

1Project management plan⁦2025-02-13⁩
2Main deliverable — stage 1⁦2025-12-01⁩
3Main deliverable — final stage⁦2026-07-05⁩
4Final report⁦2026-09-30⁩

7Key milestones

  1. Charter approved⁦2025-01-17⁩
  2. Contract signed⁦2025-04-28⁩
  3. 50% of works complete⁦2025-12-01⁩
  4. Provisional acceptance⁦2026-08-11⁩
  5. Closure⁦2026-09-30⁩

8Budget

  • Main contract⁦71.8%⁩10.2M
  • Supervision & consulting⁦14.1%⁩2M
  • Internal team⁦9.2%⁩1.3M
  • Contingency reserve (⁦5%⁩)⁦4.9%⁩700K
The owning sector’s approved budgetTotal14.2M

9Timeline

Start
2025-01-1919 Rajab 1446 AH
Baseline finish
2026-09-3019 Rabiʻ II 1448 AH
Duration
⁦20⁩ months

10Key risks

  • MediumHigh UAT defect count in the outgoing-mail module

11Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

  • Named internal staff available throughout
  • Approvals land within workflow SLAs

13Stakeholders

  • Project sponsorDecisions and funding
  • Business ownerAccepts deliverables, owns benefits
  • Projects Follow-up Office (EPMO)Governance and compliance

14Success criteria

  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • EPMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, issues, weekly statusWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Board
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close