Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-017At risk9HandoverWaterfall

Administrative Correspondence & e-Archive Platform

Add to watchlist

Automated correspondence and e-archiving, linked to the government communications network.

Budget (BAC)

SAR 14.2M

Actual cost

SAR 13.5M

⁦95%⁩ of budget

Progress

⁦95%⁩

Planned ⁦100%⁩

Estimate at completion

SAR 14.2M

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

HandoverPhase ⁦9⁩ of ⁦11⁩

Next gate:Closure30 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate2 August 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate19 February 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate10 March 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate28 April 2025Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate5 July 2026Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate11 August 2026Handover · Current phaseHandover · Current phase
  10. Gate into «Closure»DecisionNot held yetDate30 September 2026Closure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

4Achieved
0On track
0At risk
1Late
Average delay55 days
Jul 25Oct 25Jan 26Apr 26Jul 26Oct 26
Contractual
Build completePlanned: ⁦2026-03-01⁩Forecast / actual: ⁦2026-04-28⁩Delay: 58 daysG3 +58
Executive
Project plan approvedPlanned: ⁦2025-06-07⁩Forecast / actual: ⁦2025-06-27⁩Delay: 20 daysG1 +20
Payment
Final handoverPlanned: ⁦2026-09-30⁩Forecast / actual: ⁦2026-12-24⁩Delay: 85 daysG5 +85
Regulatory
Testing & acceptance completePlanned: ⁦2026-06-15⁩Forecast / actual: ⁦2026-08-28⁩Delay: 74 daysG4 +74
Project
Designs approvedPlanned: ⁦2025-09-21⁩Forecast / actual: ⁦2025-10-27⁩Delay: 36 daysG2 +36

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-06-07⁩⁦2025-06-27⁩⁦+20⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.saAchieved1Approved
Designs approvedMS-G2Project⁦2025-09-21⁩⁦2025-10-27⁩⁦+36⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-03-01⁩⁦2026-04-28⁩⁦+58⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.saAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-06-15⁩⁦2026-08-28⁩⁦+74⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.saAchieved1Approved
Final handoverMS-G5Payment⁦2026-09-30⁩⁦2026-12-24⁩⁦+85⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.saLate0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline017-D1ApprovedDana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.saMunirah A. Al-Khalidi⁦2025-04-14⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Monitoring & reporting017-D2ApprovedMunirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Financial AffairsP-018m.alkhalidi@bog.gov.saMunirah A. Al-Khalidi⁦2025-06-07⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Business requirements017-D3ApprovedMunirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Financial AffairsP-018m.alkhalidi@bog.gov.saMunirah A. Al-Khalidi⁦2025-07-30⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Solution design017-D4ApprovedSarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.saMunirah A. Al-Khalidi⁦2025-09-21⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Release 1017-D5ApprovedSarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.saMunirah A. Al-Khalidi⁦2025-11-14⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Release 2017-D6ApprovedDana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.saMunirah A. Al-Khalidi⁦2026-01-06⁩V1⁦2⁩ of ⁦2⁩
⁦1⁩–⁦6⁩ of ⁦6⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close