Administrative Correspondence & e-Archive Platform
Add to watchlistAutomated correspondence and e-archiving, linked to the government communications network.
Budget (BAC)
Actual cost
95% of budget
Progress
Planned 100%
Estimate at completion
SPI · CPI
Forecast finish
46 days behind baseline
HandoverPhase 9 of 11
Next gate:Closure30 September 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate2 August 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate19 February 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate10 March 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate28 April 2025Execution · CompleteExecution · Complete
- Gate into «Monitoring & Control»DecisionGoDate5 July 2026Monitoring & Control · CompleteMonitoring & Control · Complete
- Gate into «Handover»DecisionGoDate11 August 2026Handover · Current phaseHandover · Current phase
- Gate into «Closure»DecisionNot held yetDate30 September 2026Closure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-06-07 | 2025-06-27 | +20 days | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-09-21 | 2025-10-27 | +36 days | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-03-01 | 2026-04-28 | +58 days | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-06-15 | 2026-08-28 | +74 days | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | Achieved | 1 | Approved |
| Final handoverMS-G5 | Payment | 2026-09-30 | 2026-12-24 | +85 days | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | Late | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline017-D1 | Approved | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | Munirah A. Al-Khalidi | 2025-04-14 | V1 | 2 of 2 |
| Deliverable: Monitoring & reporting017-D2 | Approved | Munirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Financial AffairsP-018m.alkhalidi@bog.gov.sa | Munirah A. Al-Khalidi | 2025-06-07 | V1 | 2 of 2 |
| Deliverable: Business requirements017-D3 | Approved | Munirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Financial AffairsP-018m.alkhalidi@bog.gov.sa | Munirah A. Al-Khalidi | 2025-07-30 | V1 | 2 of 2 |
| Deliverable: Solution design017-D4 | Approved | Sarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.sa | Munirah A. Al-Khalidi | 2025-09-21 | V1 | 2 of 2 |
| Deliverable: Release 1017-D5 | Approved | Sarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.sa | Munirah A. Al-Khalidi | 2025-11-14 | V1 | 2 of 2 |
| Deliverable: Release 2017-D6 | Approved | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | Munirah A. Al-Khalidi | 2026-01-06 | V1 | 2 of 2 |