PRJ-2026-017At risk9HandoverWaterfall

Administrative Correspondence & e-Archive Platform

Add to watchlist

Automated correspondence and e-archiving, linked to the government communications network.

Budget (BAC)

SAR 14.2M

Actual cost

SAR 13.5M

⁦95%⁩ of budget

Progress

⁦95%⁩

Planned ⁦100%⁩

Estimate at completion

SAR 14.2M

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

HandoverPhase ⁦9⁩ of ⁦11⁩

Next gate:Closure30 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate2 August 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate19 February 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate10 March 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate28 April 2025Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate5 July 2026Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate11 August 2026Handover · Current phaseHandover · Current phase
  10. Gate into «Closure»DecisionNot held yetDate30 September 2026Closure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 14.2M split into spent, committed and left, with the estimate at completion

EAC SAR 14.2M
Revised request SAR 14.2M
  • Actual spendSAR 13.5M
  • Committed, not spentSAR 410K
  • Allotted, uncommittedSAR 0
  • Contingency availableSAR 426K

Budget

Original budgetwhen the first baseline was approved
SAR 14.2M
Approved budgetafter approved change requests
SAR 14.2M
Current budgetavailable to spend now
SAR 14.2M
Revised budgetif the pending changes are approved
SAR 14.2M

Commitments

Commitmentssigned contracts and purchase orders
SAR 13.9M
Contracts1 active contract
SAR 11.6M
Purchase orders⁦0⁩ orders
SAR 2.3M
Remaining budgetapproved less actual
SAR 710K

Spend & outlook

Actual costincluding accruals
SAR 13.5M
Accrualswork done, not yet invoiced
SAR 540K
Estimate at completionthe PM’s bottom-up forecast
SAR 14.2M
ContingencySAR 284K drawn of SAR 710K
SAR 426K

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 284K drawn of SAR 710K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 284K

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance1.101.141.141.14⁦−0.03⁩
2Analysis & design2.342.412.412.41⁦−0.07⁩
3Build5.515.685.685.68⁦−0.17⁩
4Testing & acceptance2.752.842.842.84⁦−0.09⁩
5Launch & handover2.071.831.421.91⁦+0.15⁩
Unallocated contingency0.430.000.000.21⁦+0.21⁩
Total14.2013.9013.4914.20⁦+0.00⁩

Budget split

WBS

SAR 14.2M

Budget

  • Management & governanceSAR 1.1M⁦8%⁩
  • Analysis & designSAR 2.3M⁦16%⁩
  • BuildSAR 5.5M⁦39%⁩
  • Testing & acceptanceSAR 2.8M⁦19%⁩
  • Launch & handoverSAR 2.1M⁦15%⁩
  • Unallocated contingencySAR 426K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-02-07⁩+130

SPI(t) ⁦0.83⁩ against the approved finish ⁦2026-09-30⁩

Planned valuePV
SAR 14.2M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 13.5M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 13.5M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 14.2M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.00⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−0.71⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.00
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.95
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 14.2M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 710K
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.00⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 14.2M
  • If the rest goes to planSAR 14.2M
  • At cost and schedule performanceSAR 14.2M
  • The PM’s bottom-up estimateSAR 14.2M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 14.2M

Variance at completion: ⁦+0.00⁩ SAR M