Original
Original baseline
- Finish
- 2026-09-30
- Budget
- SAR 14.2M
- 16 activities
Approved with the project plan at the planning gate.
Approved 2025-01-19 · by Sarah A. Al-Qarni
Automated correspondence and e-archiving, linked to the government communications network.
Budget (BAC)
Actual cost
95% of budget
Progress
Planned 100%
Estimate at completion
SPI · CPI
Forecast finish
46 days behind baseline
HandoverPhase 9 of 11
Next gate:Closure30 September 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-01-19 · by Sarah A. Al-Qarni
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Dana S. Al-Saleh
What changed from version A to version B
Finish
2026-09-302026-12-24
+85 days
Budget
SAR 14.2MSAR 14.2M
0.00 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference