PRJ-2026-017At risk9HandoverWaterfall

Administrative Correspondence & e-Archive Platform

Add to watchlist

Automated correspondence and e-archiving, linked to the government communications network.

Budget (BAC)

SAR 14.2M

Actual cost

SAR 13.5M

⁦95%⁩ of budget

Progress

⁦95%⁩

Planned ⁦100%⁩

Estimate at completion

SAR 14.2M

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

HandoverPhase ⁦9⁩ of ⁦11⁩

Next gate:Closure30 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate2 August 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate19 February 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate10 March 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate28 April 2025Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate5 July 2026Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate11 August 2026Handover · Current phaseHandover · Current phase
  10. Gate into «Closure»DecisionNot held yetDate30 September 2026Closure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Closure readiness

Closure planned after the forecast finish on ⁦2026-11-15⁩

A preview of what closure will need, with the planned dates, and the lessons captured so far.

0/7

Closure checklist

Seven mandatory items before any project closes.

  1. 1

    Deliverables acceptedNot started

    Final acceptance of every deliverable

    Munirah A. Al-KhalidiPlanned ⁦2026-11-05⁩

  2. 2

    Financial closureNot started

    Spend reconciled, commitments closed

    Khalid N. Al-MutairiPlanned ⁦2026-12-05⁩

  3. 3

    Contract closureNot started

    Contracts closed, retention released

    Khalid N. Al-MutairiPlanned ⁦2026-12-15⁩

  4. 4

    Documents archivedNot started

    Documents archived with classification

    Dana S. Al-SalehPlanned ⁦2026-12-10⁩

  5. 5

    Lessons learnedNot started

    Lessons-learned session

    Dana S. Al-SalehPlanned ⁦2026-11-30⁩

  6. 6

    Benefits owner assignedNot started

    Benefits handed to their owner with a measurement plan

    Munirah A. Al-KhalidiPlanned ⁦2026-11-25⁩

  7. 7

    Final report approvedNot started

    Final report and its approval

    Dana S. Al-SalehPlanned ⁦2026-12-20⁩

Post-implementation review

Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?

The review comes after closure

About three months after the forecast finish (⁦2026-11-15⁩), with the sponsor and the benefits owner.

Lessons learned

0 lessons — offered automatically to similar projects when they are created.

Knowledge base

No lessons captured yet

Capture what the team learned during delivery; closure needs at least one.

Benefits handover

Each benefit moves from the project manager to an owner who measures it after closure.

  • Faster routing of correspondence

    baseline ⁦6⁩ · now ⁦3.2⁩ · target ⁦1.5⁩ days

    ⁦62%⁩ of target realised
    Handed over at closure (current owner: Munirah A. Al-Khalidi)