AI insight
No early warning on this project
Only a 44% chance of a further slip on current trends.
Preparing staff for digital change through change champions and internal campaigns.
Budget (BAC)
Actual cost
64% of budget
Progress
Planned 72%
Estimate at completion
SAR +131K
SPI · CPI
Forecast finish
31 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control2 November 2026
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
84
Solid
Index over the last six reports
May to October 2026
No material change in the health dimensions over the period.
AI insight
Only a 44% chance of a further slip on current trends.
Generated from the live project data
The project is behind plan: 63% done against 72% planned.
SPI 0.88, CPI 0.98.
3 of 5 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 86% of budget
0 approvals and 0 open actions on this project
1 open risk, exposure SAR 250K
Impact
0 escalated
1 of 4 approved
4 members