PRJ-2026-027At risk7ExecutionHybrid

Change Management & Culture Programme

Add to watchlist

Preparing staff for digital change through change champions and internal campaigns.

Budget (BAC)

SAR 6.4M

Actual cost

SAR 4.1M

⁦64%⁩ of budget

Progress

⁦63%⁩

Planned ⁦72%⁩

Estimate at completion

SAR 6.5M

SAR +131K

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control2 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate16 May 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate23 November 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionConditional goDate6 December 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate2 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−9

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is behind plan: ⁦63%⁩ done against ⁦72%⁩ planned.

SPI ⁦0.88⁩, CPI ⁦0.98⁩.

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦86%⁩ of budget

4.1M/ 6.4M131Kprojected overrun(⁦2.0%⁩)
Actual spend
4.1M
Committed
5.5M
Approved budget
6.4M
Estimate at completion
6.5M

Next milestones

  • Provisional acceptance⁦2026-12-20⁩was ⁦2026-11-27⁩Late
  • Closure⁦2027-01-31⁩was ⁦2026-12-31⁩Late

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & issues

1 open risk, exposure SAR 250K

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0040Low middle-management participation in change activitiesProbability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium1
  • Low0

Open issues

⁦0⁩ escalated

  • No open issues

Deliverables

⁦1⁩ of ⁦4⁩ approved

  • Project management planDLV-027-1 · V1Ghada A. Al-Shahrani⁦2025-11-19⁩2025-11-1928 Jumada I 1447 AHApproved
  • Main deliverable — stage 1DLV-027-2 · V1Abdulmajeed R. Al-Dosari143 days overdue2026-06-0721 Dhuʻl-Hijjah 1447 AHIn review
  • Main deliverable — final stageDLV-027-3 · V1Abdulmajeed R. Al-DosariIn 5 days2026-11-0222 Jumada I 1448 AHIn progress
  • Final reportDLV-027-4 · V1Abdulmajeed R. Al-DosariIn 64 days2026-12-3122 Rajab 1448 AHIn progress

Team, contracts & documents

Team

4 members

Ghada A. Al-Shahrani · Director, Organisational ExcellenceSarah A. Al-Qarni · VP, Support ServicesLama S. Al-Harbi · Senior Business AnalystNouf M. Al-Balawi · Change Management Specialist
  • Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceProject managerP-029g.alshahrani@alwaha.gov.sa⁦50%⁩
  • Sarah A. Al-QarniSarah A. Al-QarniVP, Support ServicesProject sponsorP-012s.alqarni@alwaha.gov.sa⁦10%⁩
  • Lama S. Al-HarbiLama S. Al-HarbiSenior Business AnalystProcess change-impact analysisP-006l.alharbi@alwaha.gov.sa⁦15%⁩
  • Nouf M. Al-BalawiNouf M. Al-BalawiChange Management SpecialistInternal communications planP-035n.albalawi@alwaha.gov.sa⁦45%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled