PRJ-2026-027At risk7ExecutionHybrid

Change Management & Culture Programme

Add to watchlist

Preparing staff for digital change through change champions and internal campaigns.

Budget (BAC)

SAR 6.4M

Actual cost

SAR 4.1M

⁦64%⁩ of budget

Progress

⁦63%⁩

Planned ⁦72%⁩

Estimate at completion

SAR 6.5M

SAR +131K

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control2 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate16 May 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate23 November 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionConditional goDate6 December 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate2 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Team & roles

4 members, about ⁦1.2⁩ full-time equivalents

Leadership

2 members

  • Ghada A. Al-ShahraniProject manager⁦50%⁩A
  • Sarah A. Al-QarniProject sponsor⁦10%⁩R

Core team

1 member

  • Lama S. Al-HarbiProcess change-impact analysis⁦15%⁩Allocated ⁦120%⁩ across all projectsR

Specialists

1 member

  • Nouf M. Al-BalawiInternal communications plan⁦45%⁩C

A AccountableR ResponsibleC ConsultedI Informed

Stakeholders

⁦6⁩ stakeholders, ⁦4⁩ of them below the engagement needed

Power / interest matrix

Pick one to see how they are handled

Power & influence

Keep satisfied1

high power, lower interest

Manage closely4

high power and interest

Monitor0

minimal effort

Keep informed1

high interest, lower power

Sarah A. Al-QarniManage closelyAbdulmajeed R. Al-DosariManage closelyEnterprise PMOManage closelyEnd beneficiariesKeep informedFinancial Affairs AgencyKeep satisfiedKnowledge Training & Development Co.Manage closely

Interest

Project sponsor

Sarah A. Al-Qarni

Decisions and funding

Influence

Interest

Engagement level

Unaware

Resistant

Neutral

Now

Supportive

Target

Leading

A gap of ⁦1⁩ steps — needs an engagement plan.

Impact on the project
Approves gates and changes
Engagement plan
Monthly briefing
Last contact⁦2026-09-18⁩
⁦6⁩ results
Export CSV
OrganisationRoleActions
Sarah A. Al-QarniProject sponsorDecisions and fundingSupportiveLeadingGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceP-029g.alshahrani@alwaha.gov.sa⁦2026-09-18⁩
Abdulmajeed R. Al-DosariBusiness ownerAccepts deliverables, owns benefitsLeadingGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceP-029g.alshahrani@alwaha.gov.sa⁦2026-09-21⁩
Enterprise PMOGovernanceCompliance and data qualitySupportiveGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceP-029g.alshahrani@alwaha.gov.sa⁦2026-09-15⁩
Financial Affairs AgencyInternal departmentPayment approvalNeutralSupportiveHaifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@alwaha.gov.sa⁦2026-09-12⁩
Knowledge Training & Development Co.Main vendorDelivers the contracted workNeutralSupportiveGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceP-029g.alshahrani@alwaha.gov.sa⁦2026-09-22⁩
End beneficiariesBeneficiariesUsers of the outcomeNeutralSupportiveGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceP-029g.alshahrani@alwaha.gov.sa⁦2026-08-25⁩
⁦1⁩–⁦6⁩ of ⁦6⁩

Communication plan

Who needs what, when, through which channel, and who owns it.

  • Project sponsorStatus and decisions neededMonthlyMeetingGhada A. Al-Shahrani⁦2026-10-14⁩
  • Business ownerDeliverable status and acceptance datesFortnightlyEmailGhada A. Al-Shahrani⁦2026-10-02⁩
  • PMOData and indicator updatesWeeklyDashboardGhada A. Al-Shahrani⁦2026-09-29⁩
  • BeneficiariesWhat changes and whenAt milestonesNewsletterGhada A. Al-ShahraniAt launch

Coming up

By date

  1. 292026-09PMODashboard · Weekly
  2. 022026-10Business ownerEmail · Fortnightly
  3. 142026-10Project sponsorMeeting · Monthly
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close