PRJ-2026-027At risk7ExecutionHybrid

Change Management for the Digital Judiciary

Add to watchlist

Preparing judges, their staff and employees for digital work through change champions in every court and internal campaigns.

Budget (BAC)

SAR 6.4M

Actual cost

SAR 4.1M

⁦64%⁩ of budget

Progress

⁦63%⁩

Planned ⁦72%⁩

Estimate at completion

SAR 6.5M

SAR +131K

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control2 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate16 May 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate23 November 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionConditional goDate6 December 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate2 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 6.4M split into spent, committed and left, with the estimate at completion

Forecast overrun SAR 131K
EAC SAR 6.5M
Revised request SAR 6.4M
  • Actual spendSAR 4.1M
  • Committed, not spentSAR 1.4M
  • Allotted, uncommittedSAR 708K
  • Contingency availableSAR 192K

Budget

Original budgetwhen the first baseline was approved
SAR 6.4M
Approved budgetafter approved change requests
SAR 6.4M
Current budgetavailable to spend now
SAR 6.4M
Revised budgetif the pending changes are approved
SAR 6.4M

Commitments

Commitmentssigned contracts and purchase orders
SAR 5.5M
Contracts1 active contract
SAR 4.9M
Purchase orders⁦0⁩ orders
SAR 600K
Remaining budgetapproved less actual
SAR 2.3M

Spend & outlook

Actual costincluding accruals
SAR 4.1M
Accrualswork done, not yet invoiced
SAR 165K
Estimate at completionthe PM’s bottom-up forecast
SAR 6.5M
ContingencySAR 128K drawn of SAR 320K
SAR 192K

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 128K drawn of SAR 320K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 128K

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.620.650.650.65⁦−0.03⁩
2Diagnosis1.241.311.311.31⁦−0.06⁩
3Design1.861.961.961.96⁦−0.10⁩
4Implementation1.861.210.201.89⁦−0.02⁩
5Handover & knowledge transfer0.620.380.000.63⁦−0.01⁩
Unallocated contingency0.190.000.000.10⁦+0.10⁩
Total6.405.504.116.53⁦−0.13⁩

Budget split

WBS

SAR 6.4M

Budget

  • Management & governanceSAR 620.8K⁦10%⁩
  • DiagnosisSAR 1.2M⁦19%⁩
  • DesignSAR 1.9M⁦29%⁩
  • ImplementationSAR 1.9M⁦29%⁩
  • Handover & knowledge transferSAR 620.8K⁦10%⁩
  • Unallocated contingencySAR 192K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-07-13⁩+194

SPI(t) ⁦0.69⁩ against the approved finish ⁦2026-12-31⁩

Planned valuePV
SAR 6M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 4M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 4.1M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 6.4M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦−0.08⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−2.01⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
0.98
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.67
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 6.5M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 2.4M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦−0.13⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.04
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 6.5M
  • If the rest goes to planSAR 6.5M
  • At cost and schedule performanceSAR 7.7M
  • The PM’s bottom-up estimateSAR 6.5M
  • To stay within SAR 6.4M, cost performance on the rest must rise to ⁦1.04⁩ — above what has been achieved.

Estimate at completion at that performance

SAR 6.5M

Variance at completion: ⁦−0.13⁩ SAR M