Original
Original baseline
- Finish
- 2026-12-31
- Budget
- SAR 6.4M
- 15 activities
Approved with the project plan at the planning gate.
Approved 2025-11-02 · by Sarah A. Al-Qarni
Preparing judges, their staff and employees for digital work through change champions in every court and internal campaigns.
Budget (BAC)
Actual cost
64% of budget
Progress
Planned 72%
Estimate at completion
SAR +131K
SPI · CPI
Forecast finish
31 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control2 November 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-11-02 · by Sarah A. Al-Qarni
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Ghada A. Al-Shahrani
What changed from version A to version B
Finish
2026-12-312027-01-29
+29 days
Budget
SAR 6.4MSAR 6.4M
0.00 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference