PRJ-2026-027At risk7ExecutionHybrid

Change Management for the Digital Judiciary

Add to watchlist

Preparing judges, their staff and employees for digital work through change champions in every court and internal campaigns.

Budget (BAC)

SAR 6.4M

Actual cost

SAR 4.1M

⁦64%⁩ of budget

Progress

⁦63%⁩

Planned ⁦72%⁩

Estimate at completion

SAR 6.5M

SAR +131K

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control2 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate16 May 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate23 November 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionConditional goDate6 December 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate2 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

3Achieved
0On track
1At risk
1Late
Average delay62 days
Apr 26Jul 26Oct 26Jan 27
Contractual
Build completePlanned: ⁦2026-07-24⁩Forecast / actual: ⁦2026-10-26⁩Delay: 94 daysG3 +94
Executive
Project plan approvedPlanned: ⁦2026-02-14⁩Forecast / actual: ⁦2026-03-24⁩Delay: 38 daysG1 +38
Payment
Final handoverPlanned: ⁦2026-12-31⁩Forecast / actual: ⁦2027-01-29⁩Delay: 29 daysG5 +29
Regulatory
Testing & acceptance completePlanned: ⁦2026-10-12⁩Forecast / actual: ⁦2027-01-01⁩Delay: 81 daysG4 +81
Project
Designs approvedPlanned: ⁦2026-05-05⁩Forecast / actual: ⁦2026-07-11⁩Delay: 67 daysG2 +67

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-02-14⁩⁦2026-03-24⁩⁦+38⁩ daysGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceP-029g.alshahrani@bog.gov.saAchieved1Approved
Designs approvedMS-G2Project⁦2026-05-05⁩⁦2026-07-11⁩⁦+67⁩ daysGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceP-029g.alshahrani@bog.gov.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-07-24⁩⁦2026-10-26⁩⁦+94⁩ daysGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceP-029g.alshahrani@bog.gov.saAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-10-12⁩⁦2027-01-01⁩⁦+81⁩ daysGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceP-029g.alshahrani@bog.gov.saLate0Not requested
Final handoverMS-G5Payment⁦2026-12-31⁩⁦2027-01-29⁩⁦+29⁩ daysGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceP-029g.alshahrani@bog.gov.saAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline027-D1ApprovedGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceP-029g.alshahrani@bog.gov.saAbdulmajeed R. Al-Dosari⁦2026-01-05⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Monitoring & reporting027-D2ApprovedAbdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@bog.gov.saAbdulmajeed R. Al-Dosari⁦2026-02-14⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Current-state assessment027-D3ApprovedAbdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@bog.gov.saAbdulmajeed R. Al-Dosari⁦2026-03-26⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Benchmarking027-D4ApprovedSarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.saAbdulmajeed R. Al-Dosari⁦2026-05-05⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Target model027-D5ApprovedSarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.saAbdulmajeed R. Al-Dosari⁦2026-06-14⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Roadmap027-D6ApprovedGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceP-029g.alshahrani@bog.gov.saAbdulmajeed R. Al-Dosari⁦2026-07-24⁩V1⁦2⁩ of ⁦2⁩