Change Management for the Digital Judiciary
Add to watchlistPreparing judges, their staff and employees for digital work through change champions in every court and internal campaigns.
Budget (BAC)
Actual cost
64% of budget
Progress
Planned 72%
Estimate at completion
SAR +131K
SPI · CPI
Forecast finish
31 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control2 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate16 May 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate23 November 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionConditional goDate6 December 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate9 January 2026Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate2 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-02-14 | 2026-03-24 | +38 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceP-029g.alshahrani@bog.gov.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-05-05 | 2026-07-11 | +67 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceP-029g.alshahrani@bog.gov.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-07-24 | 2026-10-26 | +94 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceP-029g.alshahrani@bog.gov.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-10-12 | 2027-01-01 | +81 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceP-029g.alshahrani@bog.gov.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-12-31 | 2027-01-29 | +29 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceP-029g.alshahrani@bog.gov.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline027-D1 | Approved | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceP-029g.alshahrani@bog.gov.sa | Abdulmajeed R. Al-Dosari | 2026-01-05 | V1 | 2 of 2 |
| Deliverable: Monitoring & reporting027-D2 | Approved | Abdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@bog.gov.sa | Abdulmajeed R. Al-Dosari | 2026-02-14 | V1 | 2 of 2 |
| Deliverable: Current-state assessment027-D3 | Approved | Abdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@bog.gov.sa | Abdulmajeed R. Al-Dosari | 2026-03-26 | V1 | 2 of 2 |
| Deliverable: Benchmarking027-D4 | Approved | Sarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.sa | Abdulmajeed R. Al-Dosari | 2026-05-05 | V1 | 2 of 2 |
| Deliverable: Target model027-D5 | Approved | Sarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.sa | Abdulmajeed R. Al-Dosari | 2026-06-14 | V1 | 2 of 2 |
| Deliverable: Roadmap027-D6 | Approved | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Organisational ExcellenceP-029g.alshahrani@bog.gov.sa | Abdulmajeed R. Al-Dosari | 2026-07-24 | V1 | 2 of 2 |