Change Management for the Digital Judiciary
Add to watchlistPreparing judges, their staff and employees for digital work through change champions in every court and internal campaigns.
Budget (BAC)
Actual cost
64% of budget
Progress
Planned 72%
Estimate at completion
SAR +131K
SPI · CPI
Forecast finish
31 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control2 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate16 May 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate23 November 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionConditional goDate6 December 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate9 January 2026Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate2 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Project lifecycle and its gates
Current phase: Execution. Pick a gate on the track to review it.
- Gate into «Feasibility»DecisionGoDate16 May 2025All criteria and required documents met.IdeaComplete
- Gate into «Initiation»DecisionGoDate3 September 2025All criteria and required documents met.FeasibilityComplete
- Gate into «Planning»DecisionGoDate2 November 2025All criteria and required documents met.InitiationComplete
- Gate into «Approval»DecisionGoDate23 November 2025All criteria and required documents met.PlanningComplete
- Gate into «Procurement»DecisionConditional goDate6 December 2025Mandatory criteria met, with points to close during the next phase.ApprovalComplete
- Gate into «Execution»DecisionGoDate9 January 2026All criteria and required documents met.ProcurementComplete
- Gate into «Monitoring & Control»DecisionNot held yetDate2 November 2026ExecutionCurrent phaseCurrent phase
- Gate into «Handover»DecisionNot held yet8Monitoring & ControlNot started
- Gate into «Closure»DecisionNot held yet9HandoverNot started
- Gate into «Benefits Realization»DecisionNot held yet10ClosureNot started
- 11Benefits RealizationNot started
Operational readiness gate — into hypercare & monitoring
Gate readiness
Meets the pass mark
Automated control: no move until the criteria are met
- 1 mandatory checklist item open
- 2 required documents not approved
Checklist
4 of 7 done
- All in-scope services builtMandatory
- User acceptance testing passedMandatory
- Penetration test passed — no critical/high findingsMandatory
- Data migrated and reconciledMandatory
- Operations & support plan, SLAMandatory
- Users trained — judges, clerks and staff
- Launch rollback plan
Required documents
2 of 4 approved
- UAT reportApproved · V1
- Penetration test reportNot submitted
- Operations & support planApproved · V1
- Data migration reconciliationNot submitted
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Deliverables completeweight 30%Met
Awaiting evidence from the project team.
Quality & securityweight 30%Met
Awaiting evidence from the project team.
Operations & support readinessweight 20%Met
Awaiting evidence from the project team.
User & change readinessweight 20%
Awaiting evidence from the project team.
Approvers
Projects Steering Committee
- Dr. Abdullah S. Al-QahtaniSteering Committee chairVote pending
- Sarah A. Al-QarniProject sponsorVote pending
- Dr. Noura M. Al-OtaibiEPMO directorVote pending
- Abdulmajeed R. Al-DosariBusiness ownerVote pending