Change Management for the Digital Judiciary

Add to watchlist

Preparing judges, their staff and employees for digital work through change champions in every court and internal campaigns.

Budget (BAC)

SAR 6.4M

Actual cost

SAR 4.1M

⁦64%⁩ of budget

Progress

⁦63%⁩

Planned ⁦72%⁩

Estimate at completion

SAR 6.5M

SAR +131K

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control2 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate16 May 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate23 November 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionConditional goDate6 December 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate2 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work6.2M⁦15⁩ elements
Unallocated contingency192KSAR 320K
Budget at completion6.4MPRJ-2026-027
Weighted progress⁦63%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project453⁦2025-11-02⁩⁦2027-01-29⁩⁦63%⁩6.214.11—
1
Phase142⁦2025-11-02⁩⁦2026-03-24⁩⁦100%⁩0.620.65—
1.1
WBS element87⁦2025-11-02⁩⁦2026-01-28⁩⁦100%⁩0.310.330 / 1
1.2
WBS element87⁦2025-12-27⁩⁦2026-03-24⁩⁦100%⁩0.310.331 / 2
2
Phase142⁦2026-02-19⁩⁦2026-07-11⁩⁦100%⁩1.241.31—
2.1
WBS element87⁦2026-02-19⁩⁦2026-05-17⁩⁦100%⁩0.620.651 / 1
2.2
WBS element87⁦2026-04-15⁩⁦2026-07-11⁩⁦100%⁩0.620.651 / 2
3
Phase140⁦2026-06-08⁩⁦2026-10-26⁩⁦100%⁩1.861.96—
3.1
WBS element87⁦2026-06-08⁩⁦2026-09-03⁩⁦100%⁩0.930.981 / 1
3.2
WBS element85⁦2026-08-02⁩⁦2026-10-26⁩⁦100%⁩0.930.981 / 2
4
Phase185⁦2026-06-30⁩⁦2027-01-01⁩⁦10%⁩1.860.20—
4.1
WBS element171⁦2026-06-30⁩⁦2026-12-18⁩⁦20%⁩0.930.201 / 1
4.2
WBS element23⁦2026-12-09⁩⁦2027-01-01⁩⁦0%⁩0.93—1 / 2
5
Phase37⁦2026-12-23⁩⁦2027-01-29⁩⁦0%⁩0.62——
5.1
WBS element23⁦2026-12-23⁩⁦2027-01-15⁩⁦0%⁩0.31—1 / 1
5.2
WBS element23⁦2027-01-06⁩⁦2027-01-29⁩⁦0%⁩0.31—1 / 1
Total⁦63%⁩6.214.11