Add to watchlistPreparing judges, their staff and employees for digital work through change champions in every court and internal campaigns.
Budget (BAC)
Actual cost
64% of budget
Progress
Planned 72%
Estimate at completion
SAR +131K
SPI · CPI
Forecast finish
31 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control2 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate16 May 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate23 November 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionConditional goDate6 December 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate9 January 2026Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate2 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+29 days vs approved
- Critical activities
- 5
- of 6 open activities
- Late activities
- 4
- past their baseline finish
- Schedule performance
- 0.67
- earned ÷ planned value
- Next milestone
- in 65 days
- Testing & acceptance complete
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
21 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 6 open activities, data date 2026-10-28
“Wave 1” needs a pace 9.4× faster than it has kept
It earned 20% in 120 days; the forecast assumes the rest in 51 days. At the pace so far it finishes on 2028-02-20.
Milestones slip 62 days on average — and it is getting worse
Each milestone’s slip in days, in date order; the later ones slip more than the early ones.
The critical chain
In date order, to final acceptance