PRJ-2026-027At risk7ExecutionHybrid

Change Management for the Digital Judiciary

Add to watchlist

Preparing judges, their staff and employees for digital work through change champions in every court and internal campaigns.

Budget (BAC)

SAR 6.4M

Actual cost

SAR 4.1M

⁦64%⁩ of budget

Progress

⁦63%⁩

Planned ⁦72%⁩

Estimate at completion

SAR 6.5M

SAR +131K

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control2 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate16 May 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate23 November 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionConditional goDate6 December 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate2 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+29⁩ days vs approved

Original baseline⁦2026-12-31⁩
Approved baseline⁦2026-12-31⁩
Current forecast⁦2027-01-29⁩
By earned schedule⁦2027-07-13⁩
Critical activities
5
of ⁦6⁩ open activities
Late activities
4
past their baseline finish
Schedule performance
0.67
earned ÷ planned value
Next milestone
in 65 days
Testing & acceptance complete
Expand allCollapse all
Activity
Change Management for the Digital JudiciaryPlanned: ⁦2025-11-02⁩ → ⁦2026-12-31⁩Forecast: ⁦2025-11-02⁩ → ⁦2027-01-29⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-11-02⁩ → ⁦2026-02-14⁩Actual: ⁦2025-11-02⁩ → ⁦2026-03-24⁩
Project plan & baselinePlanned: ⁦2025-11-02⁩ → ⁦2026-01-05⁩Actual: ⁦2025-11-02⁩ → ⁦2026-01-28⁩
Monitoring & reportingPlanned: ⁦2025-12-12⁩ → ⁦2026-02-14⁩Actual: ⁦2025-12-27⁩ → ⁦2026-03-24⁩
Project plan approvedPlanned: ⁦2026-02-14⁩ → ⁦2026-02-14⁩Actual: ⁦2026-03-24⁩ → ⁦2026-03-24⁩Project plan approved
DiagnosisPlanned: ⁦2026-01-21⁩ → ⁦2026-05-05⁩Actual: ⁦2026-02-19⁩ → ⁦2026-07-11⁩
Current-state assessmentPlanned: ⁦2026-01-21⁩ → ⁦2026-03-26⁩Actual: ⁦2026-02-19⁩ → ⁦2026-05-17⁩
BenchmarkingPlanned: ⁦2026-03-02⁩ → ⁦2026-05-05⁩Actual: ⁦2026-04-15⁩ → ⁦2026-07-11⁩
Designs approvedPlanned: ⁦2026-05-05⁩ → ⁦2026-05-05⁩Actual: ⁦2026-07-11⁩ → ⁦2026-07-11⁩Designs approved
DesignPlanned: ⁦2026-04-11⁩ → ⁦2026-07-24⁩Actual: ⁦2026-06-08⁩ → ⁦2026-10-26⁩
Target modelPlanned: ⁦2026-04-11⁩ → ⁦2026-06-14⁩Actual: ⁦2026-06-08⁩ → ⁦2026-09-03⁩
RoadmapPlanned: ⁦2026-05-21⁩ → ⁦2026-07-24⁩Actual: ⁦2026-08-02⁩ → ⁦2026-10-26⁩
Build completePlanned: ⁦2026-07-24⁩ → ⁦2026-07-24⁩Actual: ⁦2026-10-26⁩ → ⁦2026-10-26⁩Build complete
ImplementationPlanned: ⁦2026-06-30⁩ → ⁦2026-10-12⁩Forecast: ⁦2026-06-30⁩ → ⁦2027-01-01⁩Float: ⁦0⁩d
Wave 1Planned: ⁦2026-06-30⁩ → ⁦2026-09-02⁩Forecast: ⁦2026-06-30⁩ → ⁦2026-12-18⁩Float: ⁦0⁩d+107
Wave 2Planned: ⁦2026-08-09⁩ → ⁦2026-10-12⁩Forecast: ⁦2026-12-09⁩ → ⁦2027-01-01⁩Float: ⁦0⁩d+81
Testing & acceptance completePlanned: ⁦2026-10-12⁩ → ⁦2026-10-12⁩Forecast: ⁦2027-01-01⁩ → ⁦2027-01-01⁩Float: ⁦28⁩dTesting & acceptance complete
Handover & knowledge transferPlanned: ⁦2026-09-18⁩ → ⁦2026-12-31⁩Forecast: ⁦2026-12-23⁩ → ⁦2027-01-29⁩Float: ⁦0⁩d
Knowledge transferPlanned: ⁦2026-09-18⁩ → ⁦2026-11-21⁩Forecast: ⁦2026-12-23⁩ → ⁦2027-01-15⁩Float: ⁦0⁩d+55
Final reportPlanned: ⁦2026-10-28⁩ → ⁦2026-12-31⁩Forecast: ⁦2027-01-06⁩ → ⁦2027-01-29⁩Float: ⁦0⁩d+29
Final handoverPlanned: ⁦2026-12-31⁩ → ⁦2026-12-31⁩Forecast: ⁦2027-01-29⁩ → ⁦2027-01-29⁩Float: ⁦0⁩dFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦21⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦6⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦4⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Wave 1” needs a pace ⁦9.4⁩× faster than it has kept

It earned ⁦20%⁩ in 120 days; the forecast assumes the rest in 51 days. At the pace so far it finishes on ⁦2028-02-20⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 62 days on average — and it is getting worse

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

38
67
94
81
29
G1G2G3G4G5

The critical chain

In date order, to final acceptance