Board of GrievancesMunjaz10My actionsNotifications

Business case — Mueen Release 4

ConfidentialApprovedV2

The economic and technical case for Mueen Release ⁦4⁩: three options, NPV, payback and a sensitivity analysis.

More
Showing version:

Confidential

Kingdom of Saudi Arabia

Board of Grievances

Projects Follow-up Office (EPMO)

Code
DOC-0202
Version
V2
Date
2024-09-15

Business case — Mueen Release ⁦4⁩

Mueen Digital Platform — Release 4

⁦1⁩. Problem & opportunity

This case addresses the need for Mueen Digital Platform — Release ⁦4⁩ and compares three options on cost, value and risk.

Project
Mueen Digital Platform — Release ⁦4⁩ (⁦PRJ-2026-014⁩)
Project manager
Eng. Sultan F. Al-Ghamdi
Budget
SAR ⁦86.4M⁩
Progress
⁦58%⁩ actual against ⁦67%⁩ planned
Forecast finish
⁦2027-05-12⁩

⁦2⁩. Options

OptionCostNPVRecommendation
Do nothing—NegativeRejected
PartialSAR ⁦51.8M⁩LowFallback
Full solutionSAR ⁦86.4M⁩HighestRecommended

⁦3⁩. Sensitivity

NPV stays positive up to an ⁦18%⁩ cost overrun or a full year’s delay in benefits.

Prepared by

Faisal A. Al-Shehri

Project manager

Eng. Sultan F. Al-Ghamdi
Issued from Munjaz — valid only once approved electronically1 / 1

Confidential

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close