Board of GrievancesMunjaz10My actionsNotifications

RSK-0006Mueen Digital Platform — Release 4

Possible critical findings in the pre-launch penetration test

12MediumOpen

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Out-of-date open-source components in the integration layer that carries classified case data

Preventive controls

  • Automated vulnerability scanning in the deployment pipeline
  • An early penetration test on pre-production

2 / 2

Event

Possible critical findings in the pre-launch penetration test

12MediumTrigger

Any critical finding, or more than five high findings

Contingency

A two-week vendor fix squad after the report

Impact

Security sign-off postponed and launch delayed by at least four weeks, with a risk of exposing parties’ data

SAR 600K

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
12Medium

Residual

5
4
3
2
1
1
2
3
4
5
4Low

Exposure

SAR 600K

Residual

⁦67⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the EPMO director

Last reviewed 8 days ago · Outside the engine — below «high»

  1. Project manager

    Current level

    Eng. Sultan F. Al-Ghamdi

    Currently followed up here
  2. 2

    Programme manager

    Eng. Reem K. Al-Dosari

  3. 3

    EPMO director

    Dr. Noura M. Al-Otaibi

  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the EPMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • Automated vulnerability scanning in the deployment pipeline

    Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.sa
    In progressIn 18 days2026-11-155 Jumada II 1448 AH
  • An early penetration test on pre-production

    Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.sa
    Not startedIn 34 days2026-12-0121 Jumada II 1448 AH

Trigger

Any critical finding, or more than five high findings

Contingency

A two-week vendor fix squad after the report

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close