Mueen build & run contract

Mueen Digital Platform — Release 4

The parties

This contract is made between the Board of Grievances (first party) and the contractor named in the data sheet (second party), under the Government Tenders and Procurement Law and its regulations.

Project
Mueen Digital Platform — Release ⁦4⁩ (⁦PRJ-2026-014⁩)
Project manager
Eng. Sultan F. Al-Ghamdi
Budget
SAR ⁦86.4M⁩
Progress
⁦58%⁩ actual against ⁦67%⁩ planned
Forecast finish
⁦2027-05-12⁩

Key terms

  • Delay penalty ⁦0.5%⁩ a week, capped at ⁦10%⁩ of the contract value
  • A ⁦5%⁩ performance bond valid until final handover
  • ⁦10%⁩ retention on every certificate

Addendum ⁦1⁩

This addendum amends the payment schedule and adds complementary works within ⁦10%⁩ of the contract value.

Prepared by

Khalid N. Al-Mutairi

Project manager

Eng. Sultan F. Al-Ghamdi
Issued from Munjaz — valid only once approved electronically1 / 1