Internal
Kingdom of Saudi Arabia
Al-Waha Region Development Authority
Enterprise Project Management Office
- Code
- DOC-0204
- Version
- V1
- Date
- 2026-10-27
Project status report — October 2026
Unified Digital Services Platform
1. Executive summary
This report gives the position of Unified Digital Services Platform to date: 58% complete against 67% planned, SPI 0.87, CPI 0.96, and an estimate at completion of SAR 90.0M.
- Project
- Unified Digital Services Platform (PRJ-2026-014)
- Project manager
- Eng. Sultan F. Al-Ghamdi
- Budget
- SAR 86.4M
- Progress
- 58% actual against 67% planned
- Forecast finish
- 2027-05-12
2. Key findings
- All planned milestones of the period met except one deferred
- Actual spend rose in line with the work done
- Three high risks under treatment, each with a named owner
3. Recommendations & decisions needed
- Approve the proposed treatment of the high risks
- Track the open findings with the vendor weekly
Prepared by
Eng. Sultan F. Al-Ghamdi
Internal