Mueen Release 4 — weekly
Weekly project team meeting and recovery-plan follow-up.
Held on
26 October 202609:30 – 10:35
- Held
- Minutes written
- Published
- Approved
Project meeting — no quorum required
Agenda
60 of 60 min
Wave 1 progress (24 judicial services)
For informationEng. Sultan F. Al-Ghamdi
20 min
Vendor integration engineer shortfall
DiscussionHussam T. Al-Qurashi
25 min
Nafath test environment readiness
DiscussionHussam T. Al-Qurashi
15 min
Minutes
Saved as you type
Decisions & votes
No decisions recorded
Record the decision and put it to a vote if needed.
Action items
They show in the register and on the owner’s calendar
- Vendor to submit a replacement plan for integration engineers within a weekOpenIn 5 days2026-11-0222 Jumada I 1448 AH
ACT-0301Eng. Sultan F. Al-Ghamdi
Attendance & quorum
Project meeting — no quorum required
- Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Mueen Platform — Release 4GuestP-005s.alghamdi@bog.gov.saPresent
- Eng. Reem K. Al-DosariEng. Reem K. Al-DosariHead of the Mueen Platform Office & Digital Judicial Services Programme ManagerGuestP-004r.aldosari@bog.gov.saRemote
- Lama S. Al-HarbiLama S. Al-HarbiSenior Business Analyst — Judicial ProceduresGuestP-006l.alharbi@bog.gov.saPresent
- Hussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationGuestP-030h.alqurashi@bog.gov.saPresent
- Joud N. Al-AhmadiJoud N. Al-AhmadiQA & Testing SpecialistGuestP-033j.alahmadi@bog.gov.saPresent
- Maha F. Al-KhathamiMaha F. Al-KhathamiFront-end Developer (Contractor)GuestP-044m.alkhathami@bog.gov.saApologised
- Karim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOGuestP-041k.haddad@bog.gov.saRemote
Attachments
1 file
- Mueen-R4-weekly-43.pdfEng. Sultan F. Al-Ghamdi · 920 KB