10My actionsNotifications

Updated recovery plan

InternalDraftV2

The updated recovery plan to win back the ⁦42-day⁩ slip: an extra integration sprint, a simulator, a reinforced vendor team.

More
Showing version:

Internal

Kingdom of Saudi Arabia

Al-Waha Region Development Authority

Enterprise Project Management Office

Code
DOC-0205
Version
V2
Date
2026-10-25

Updated recovery plan

Unified Digital Services Platform

⁦1⁩. Where we stand

Earned progress is ⁦58%⁩ against ⁦67%⁩ planned; SPI ⁦0.87⁩, CPI ⁦0.96⁩. The forecast finish is ⁦2027-05-12⁩ instead of ⁦2027-03-31⁩ — a ⁦42-day⁩ slip — with a ⁦74%⁩ chance of further delay within ⁦45⁩ days if nothing is done.

⁦2⁩. Root causes

  • Integration agreements with Nafath and SADAD ⁦11⁩ weeks late
  • Two vendor integration engineers left at the peak of the work
  • The Nafath test environment down nine days with no local fallback

⁦3⁩. Recovery actions

ActionOwnerDueExpected effect
A dedicated two-week integration sprintHussam T. Al-Qurashi⁦2026-11-20⁩⁦14⁩ days recovered
National-interface simulatorEng. Saad M. Al-Dosari⁦2026-11-12⁩Removes the stoppage risk
Two named engineers added to the vendor teamEng. Sultan F. Al-Ghamdi⁦2026-11-05⁩⁦18⁩ days recovered
A parallel UAT trackJoud N. Al-Ahmadi⁦2026-12-01⁩⁦10⁩ days recovered

⁦4⁩. Financial effect

Budget at completion
SAR ⁦86.4M⁩
Estimate at completion
SAR ⁦90.0M⁩
Cost of the recovery actions
SAR ⁦1.9M⁩ from contingency
Target finish after recovery
⁦2027-04-10⁩

Asked of the approver: approve the plan, release SAR ⁦1.9M⁩ from the project contingency, and send a letter to the Digital Government Authority to extend the Nafath test environment.

Project manager

Eng. Sultan F. Al-Ghamdi

Programme manager

Eng. Reem K. Al-Dosari

CEO

Eng. Abdullah S. Al-Qahtani
Issued from Munjaz — valid only once approved electronically1 / 1

Internal

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close