Board of GrievancesMunjaz10My actionsNotifications

RSK-0002Mueen Digital Platform — Release 4

Shortage of integration and back-end engineers on the vendor team

16HighEscalated

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

The vendor pulled two integration engineers to another client, and back-end engineers are scarce on the market

Preventive controls

  • Formal letter to the vendor to restore the contractual staffing within 10 days
  • Change request to add integration capacity for four months
  • Apply the clause 14 staffing penalty if not resolved

1 / 3

Event

Shortage of integration and back-end engineers on the vendor team

16HighTrigger

The two replacements have not joined by 2026-11-05

Contingency

Second two engineers from the Board’s IT integration team for eight weeks

Impact

Team velocity down 30%; Nafath, Government Service Bus and wave 1 services slip

SAR 1.9M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
16High

Residual

5
4
3
2
1
1
2
3
4
5
6Low

Exposure

SAR 1.9M

Residual

⁦63⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the EPMO director

Last reviewed 2 days ago

  1. Project manager

    Eng. Sultan F. Al-Ghamdi

    Currently followed up here
  2. Programme manager

    Current level

    Eng. Reem K. Al-Dosari

    Automatically at 15 days unreviewed · in 13 days
  3. 3

    EPMO director

    Dr. Noura M. Al-Otaibi

    Automatically at 20 days unreviewed · in 18 days
  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the EPMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦2⁩ of ⁦3⁩ done
  • Formal letter to the vendor to restore the contractual staffing within 10 days

    Khalid N. Al-MutairiKhalid N. Al-MutairiSenior Finance & Contracts SpecialistP-007k.almutairi@bog.gov.sa
    Done⁦2026-10-20⁩2026-10-209 Jumada I 1448 AH
  • Change request to add integration capacity for four months

    Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Mueen Platform — Release 4P-005s.alghamdi@bog.gov.sa
    Done⁦2026-10-26⁩2026-10-2615 Jumada I 1448 AH
  • Apply the clause 14 staffing penalty if not resolved

    Khalid N. Al-MutairiKhalid N. Al-MutairiSenior Finance & Contracts SpecialistP-007k.almutairi@bog.gov.sa
    Not startedIn 8 days2026-11-0525 Jumada I 1448 AH

Trigger

The two replacements have not joined by 2026-11-05

Contingency

Second two engineers from the Board’s IT integration team for eight weeks

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close