Internal
Kingdom of Saudi Arabia
Al-Waha Region Development Authority
Enterprise Project Management Office
- Code
- DOC-0201
- Version
- V3
- Date
- 2025-02-16
Unified Digital Services Platform — project charter
Unified Digital Services Platform
1. Purpose
Bring the authority’s digital services into one platform with a single front door, connected to the national platforms, cutting the time and cost of every transaction — delivering the strategic objective «raise digital-service maturity».
2. Objectives
- Bring 68 authority services into one platform with a single beneficiary journey
- Cut average licence turnaround from 21 days to 5
- Lift beneficiary satisfaction with digital services to 88%
- Reduce cost per transaction by 60%
3. Scope
- A unified web portal compliant with Digital Government Authority standards
- Single sign-on through Nafath and payments through SADAD
- A configurable, no-code workflow and forms engine
- Migration of beneficiary data and open requests from legacy systems
- Change management and training for 420 staff
Out of scope
- The mobile app (separate project PRJ-2026-015)
- Re-engineering procedures that need regulatory changes
- Services of other government entities
4. Success criteria
- 68 services live on the platform at close
- 99.9% availability in the first six months
- Penetration test passed with no critical or high findings
- 70% of walk-in transactions moved online within 12 months
5. Assumptions & constraints
- Nafath and SADAD test environments available as agreed
- Process owners sign off requirements within 10 working days
- The vendor’s named team stays for the whole build
- Approved budget SAR 86.4M including VAT
- Hosting on the government cloud inside the Kingdom only
- Compliance with the ECC and the Personal Data Protection Law
6. Governance & budget
- Sponsor
- Eng. Majed S. Al-Rasheed
- Project manager
- Eng. Sultan F. Al-Ghamdi
- Approved budget
- SAR 86.4M
- Duration
- 2025-02-01 to 2027-03-31
- Overseeing committee
- Digital Transformation Steering Committee
The initiation gate approved the charter with two conditions: a full-time project manager within two weeks, and written commitment from the process-owning departments to sign off requirements within ten working days.
Project manager
PMO director
Sponsor