BOG/2024/011
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SAR 4.2M — if approved the value becomes SAR 1.1B
41% of the current value paid
Paid
438.2Mof a current value of SAR 1.1B
Value of each certificate
The last 14 — gross and net
Approved: 27
Count: 28 · in the approval chain: 1
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 28September 2026 | 2026-10-07 | 14.8M | 1.5M | 1.5M | 1.8M | 13.6M | In review | |
| Certificate 27August 2026 | 2026-09-07 | 16.9M | 1.7M | 1.7M | 2M | 15.5M | Approved | |
| Certificate 26July 2026 | 2026-08-06 | 6.9M | 685K | 685K | 822K | 6.3M | Approved | |
| Certificate 25June 2026 | 2026-07-05 | 8.3M | 827K | 827K | 992.4K | 7.6M | Approved | |
| Certificate 24May 2026 | 2026-06-02 | 11M | 1.1M | 1.1M | 1.3M | 10.1M | Approved | |
| Certificate 23April 2026 | 2026-05-01 | 12.8M | 1.3M | 1.3M | 1.5M | 11.8M | Approved | |
| Certificate 22March 2026 | 2026-03-29 | 13.1M | 1.3M | 1.3M | 1.6M | 12M | Approved | |
| Certificate 21February 2026 | 2026-02-25 | 17.2M | 1.7M | 1.7M | 2.1M | 15.9M | Approved | |
| Certificate 20January 2026 | 2026-01-23 | 16.9M | 1.7M | 1.7M | 2M | 15.5M | Approved | |
| Certificate 19December 2025 | 2025-12-22 | 17.6M | 1.8M | 1.8M | 2.1M | 16.2M | Approved | |
| Certificate 18October 2025 | 2025-11-19 | 21.9M | 2.2M | 2.2M | 2.6M | 20.1M | Approved | |
| Certificate 17September 2025 | 2025-10-18 | 19M | 1.9M | 1.9M | 2.3M | 17.4M | Approved | |
| Certificate 16August 2025 | 2025-09-15 | 21.6M | 2.2M | 2.2M | 2.6M | 19.8M | Approved | |
| Certificate 15July 2025 | 2025-08-14 | 23.6M | 2.4M | 2.4M | 2.8M | 21.7M | Approved | |
| Certificate 14June 2025 | 2025-07-12 | 19.7M | 2M | 2M | 2.4M | 18.1M | Approved | |
| Certificate 13May 2025 | 2025-06-10 | 23.7M | 2.4M | 2.4M | 2.8M | 21.8M | Approved | |
| Certificate 12April 2025 | 2025-05-08 | 22.3M | 2.2M | 2.2M | 2.7M | 20.5M | Approved | |
| Certificate 11March 2025 | 2025-04-06 | 19.4M | 1.9M | 1.9M | 2.3M | 17.9M | Approved | |
| Certificate 10February 2025 | 2025-03-04 | 22.9M | 2.3M | 2.3M | 2.7M | 21M | Approved | |
| Certificate 9January 2025 | 2025-01-31 | 18.9M | 1.9M | 1.9M | 2.3M | 17.4M | Approved | |
| Certificate 8December 2024 | 2024-12-29 | 17.9M | 1.8M | 1.8M | 2.2M | 16.5M | Approved | |
| Certificate 7November 2024 | 2024-11-27 | 19M | 1.9M | 1.9M | 2.3M | 17.5M | Approved | |
| Certificate 6October 2024 | 2024-10-25 | 14.5M | 1.5M | 1.5M | 1.7M | 13.4M | Approved | |
| Certificate 5September 2024 | 2024-09-23 | 14.5M | 1.5M | 1.5M | 1.7M | 13.4M | Approved | |
| Certificate 4August 2024 | 2024-08-21 | 13.1M | 1.3M | 1.3M | 1.6M | 12M | Approved | |
| Certificate 3June 2024 | 2024-07-20 | 9.9M | 990K | 990K | 1.2M | 9.1M | Approved | |
| Certificate 2May 2024 | 2024-06-17 | 9M | 904K | 904K | 1.1M | 8.3M | Approved | |
| Certificate 1April 2024 | 2024-05-16 | 6.7M | 674K | 674K | 808.8K | 6.2M | Approved |