Board of GrievancesMunjaz10My actionsNotifications

Certificate ⁦6⁩ — October 2024

Board of Grievances headquarters, Riyadh — construction

Kingdom of Saudi Arabia

Board of Grievances

General Directorate of Financial Affairs — Contracts & Procurement

Certificate no.
6
Date
⁦2024-10-25⁩
Hijri
22 Rabiʻ II 1446 AH
Reference
PAY-2024-011-06

Interim payment certificate no. (⁦6⁩)

For the work of October 2024

Contract number
BOG/2024/011
Etimad reference
2401780147
Contract
Board of Grievances headquarters, Riyadh — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
Board of Grievances Headquarters, Riyadh
Contract period
⁦2024-04-01⁩ — ⁦2027-06-30⁩
Original contract value
1,020,000,000
Current contract value
1,058,500,000including variations of SAR 38.5M

Certificate summary (SAR)

1Total value of work completed to date67,810,000
2Less: previous certificates(53,270,000)
3Value of work in this certificate14,540,000
4Less: retention (⁦10%⁩)(1,454,000)
5Less: advance payment recovery (⁦10%⁩)(1,454,000)
6Less: delay and breach penalties0
7Total deductions(2,908,000)
8Net before VAT11,632,000
9Add: value added tax (15%)1,744,800
10Net amount payable to the contractor13,376,800

Amount in words: Thirteen million three hundred seventy-six thousand eight hundred Saudi riyals only

Retention held up to this certificate: SAR 6.8M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation74,095,0008,641,0002,311,00010,952,000⁦15%⁩
Earthworks & foundations190,530,00013,467,0003,621,00017,088,000⁦9%⁩
Concrete & structural works328,135,00018,161,0004,962,00023,123,000⁦7%⁩
Mechanical, electrical & plumbing254,040,0008,906,0002,486,00011,392,000⁦4%⁩
Finishes & external works158,775,0003,568,0001,009,0004,577,000⁦3%⁩
Testing & commissioning52,925,000527,000151,000678,000⁦1%⁩
Total1,058,500,00053,270,00014,540,00067,810,000⁦6%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2024-10-25⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2024-10-27⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2024-10-30⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2024-11-02⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2024-11-05⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2024-10-25⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2024-10-27⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2024-10-30⁩

    Eng. Ahmed Y. Asiri · Director, Court Complexes

    Took 3 days

  4. Payment order prepared⁦2024-11-02⁩

    Khalid N. Al-Mutairi · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2024-11-05⁩

    Dr. Abdullah S. Al-Qahtani · President of the Board of Grievances

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Dr. Abdullah S. Al-Qahtani

Certificate history

5 November 2024

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2024-11-05 13:00

2 November 2024

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2024-11-02 13:00

30 October 2024

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2024-10-30 13:00

27 October 2024

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2024-10-27 13:00

25 October 2024

  1. Approval: Contractor signed “Certificate submitted”

    2024-10-25 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close