Board of GrievancesMunjaz10My actionsNotifications

Certificate ⁦23⁩ — April 2026

Board of Grievances headquarters, Riyadh — construction

Kingdom of Saudi Arabia

Board of Grievances

General Directorate of Financial Affairs — Contracts & Procurement

Certificate no.
23
Date
⁦2026-05-01⁩
Hijri
14 Dhuʻl-Qiʻdah 1447 AH
Reference
PAY-2024-011-23

Interim payment certificate no. (⁦23⁩)

For the work of April 2026

Contract number
BOG/2024/011
Etimad reference
2401780147
Contract
Board of Grievances headquarters, Riyadh — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
Board of Grievances Headquarters, Riyadh
Contract period
⁦2024-04-01⁩ — ⁦2027-06-30⁩
Original contract value
1,020,000,000
Current contract value
1,058,500,000including variations of SAR 38.5M

Certificate summary (SAR)

1Total value of work completed to date395,190,000
2Less: previous certificates(382,370,000)
3Value of work in this certificate12,820,000
4Less: retention (⁦10%⁩)(1,282,000)
5Less: advance payment recovery (⁦10%⁩)(1,282,000)
6Less: delay and breach penalties0
7Total deductions(2,564,000)
8Net before VAT10,256,000
9Add: value added tax (15%)1,538,400
10Net amount payable to the contractor11,794,400

Amount in words: Eleven million seven hundred ninety-four thousand four hundred Saudi riyals only

Retention held up to this certificate: SAR 39.5M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation74,095,00062,001,0001,822,00063,823,000⁦86%⁩
Earthworks & foundations190,530,00096,643,0002,945,00099,588,000⁦52%⁩
Concrete & structural works328,135,000130,361,0004,399,000134,760,000⁦41%⁩
Mechanical, electrical & plumbing254,040,00063,952,0002,440,00066,392,000⁦26%⁩
Finishes & external works158,775,00025,626,0001,049,00026,675,000⁦17%⁩
Testing & commissioning52,925,0003,787,000165,0003,952,000⁦7%⁩
Total1,058,500,000382,370,00012,820,000395,190,000⁦37%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2026-05-01⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-05-03⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2026-05-06⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-05-09⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-05-12⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-05-01⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2026-05-03⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-05-06⁩

    Eng. Ahmed Y. Asiri · Director, Court Complexes

    Took 3 days

  4. Payment order prepared⁦2026-05-09⁩

    Khalid N. Al-Mutairi · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-05-12⁩

    Dr. Abdullah S. Al-Qahtani · President of the Board of Grievances

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Dr. Abdullah S. Al-Qahtani

Certificate history

12 May 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-05-12 13:00

9 May 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-05-09 13:00

6 May 2026

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2026-05-06 13:00

3 May 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-05-03 13:00

1 May 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-05-01 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close