Kingdom of Saudi Arabia
Board of Grievances
General Directorate of Financial Affairs — Contracts & Procurement
- Certificate no.
- 27
- Date
- 2026-09-07
- Hijri
- 25 Rabiʻ I 1448 AH
- Reference
- PAY-2026-005
Interim payment certificate no. (27)
For the work of August 2026
- Contract number
- BOG/2024/011
- Etimad reference
- 2401780147
- Contract
- Board of Grievances headquarters, Riyadh — construction
- Contractor
- Al-Bunyan Al-Rasekh Contracting Co.
- Contractor VAT number
- 310102487310003
- Project
- Board of Grievances Headquarters, Riyadh
- Contract period
- 2024-04-01 — 2027-06-30
- Original contract value
- 1,020,000,000
- Current contract value
- 1,058,500,000including variations of SAR 38.5M
Certificate summary (SAR)
| 1 | Total value of work completed to date | 438,200,000 |
| 2 | Less: previous certificates | (421,300,000) |
| 3 | Value of work in this certificate | 16,900,000 |
| 4 | Less: retention (10%) | (1,690,000) |
| 5 | Less: advance payment recovery (10%) | (1,690,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (3,380,000) |
| 8 | Net before VAT | 13,520,000 |
| 9 | Add: value added tax (15%) | 2,028,000 |
| 10 | Net amount payable to the contractor | 15,548,000 |
Amount in words: Fifteen million five hundred forty-eight thousand Saudi riyals only
Retention held up to this certificate: SAR 43.8M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 74,095,000 | 68,417,000 | 2,352,000 | 70,769,000 | 96% |
| Earthworks & foundations | 190,530,000 | 106,601,000 | 3,825,000 | 110,426,000 | 58% |
| Concrete & structural works | 328,135,000 | 143,621,000 | 5,805,000 | 149,426,000 | 46% |
| Mechanical, electrical & plumbing | 254,040,000 | 70,344,000 | 3,274,000 | 73,618,000 | 29% |
| Finishes & external works | 158,775,000 | 28,160,000 | 1,419,000 | 29,579,000 | 19% |
| Testing & commissioning | 52,925,000 | 4,157,000 | 225,000 | 4,382,000 | 8% |
| Total | 1,058,500,000 | 421,300,000 | 16,900,000 | 438,200,000 | 41% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Hamad S. Al-Hajri
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Ahmed Y. Asiri
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani