Kingdom of Saudi Arabia
Board of Grievances
General Directorate of Financial Affairs — Contracts & Procurement
- Certificate no.
- 26
- Date
- 2026-08-06
- Hijri
- 23 Safar 1448 AH
- Reference
- PAY-2024-011-26
Interim payment certificate no. (26)
For the work of July 2026
- Contract number
- BOG/2024/011
- Etimad reference
- 2401780147
- Contract
- Board of Grievances headquarters, Riyadh — construction
- Contractor
- Al-Bunyan Al-Rasekh Contracting Co.
- Contractor VAT number
- 310102487310003
- Project
- Board of Grievances Headquarters, Riyadh
- Contract period
- 2024-04-01 — 2027-06-30
- Original contract value
- 1,020,000,000
- Current contract value
- 1,058,500,000including variations of SAR 38.5M
Certificate summary (SAR)
| 1 | Total value of work completed to date | 421,300,000 |
| 2 | Less: previous certificates | (414,450,000) |
| 3 | Value of work in this certificate | 6,850,000 |
| 4 | Less: retention (10%) | (685,000) |
| 5 | Less: advance payment recovery (10%) | (685,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (1,370,000) |
| 8 | Net before VAT | 5,480,000 |
| 9 | Add: value added tax (15%) | 822,000 |
| 10 | Net amount payable to the contractor | 6,302,000 |
Amount in words: Six million three hundred two thousand Saudi riyals only
Retention held up to this certificate: SAR 42.1M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 74,095,000 | 67,079,000 | 961,000 | 68,040,000 | 92% |
| Earthworks & foundations | 190,530,000 | 104,608,000 | 1,560,000 | 106,168,000 | 56% |
| Concrete & structural works | 328,135,000 | 141,311,000 | 2,352,000 | 143,663,000 | 44% |
| Mechanical, electrical & plumbing | 254,040,000 | 69,460,000 | 1,318,000 | 70,778,000 | 28% |
| Finishes & external works | 158,775,000 | 27,869,000 | 569,000 | 28,438,000 | 18% |
| Testing & commissioning | 52,925,000 | 4,123,000 | 90,000 | 4,213,000 | 8% |
| Total | 1,058,500,000 | 414,450,000 | 6,850,000 | 421,300,000 | 40% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Hamad S. Al-Hajri
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Ahmed Y. Asiri
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani