Board of GrievancesMunjaz10My actionsNotifications

Certificate ⁦25⁩ — June 2026

Board of Grievances headquarters, Riyadh — construction

Kingdom of Saudi Arabia

Board of Grievances

General Directorate of Financial Affairs — Contracts & Procurement

Certificate no.
25
Date
⁦2026-07-05⁩
Hijri
20 Muharram 1448 AH
Reference
PAY-2024-011-25

Interim payment certificate no. (⁦25⁩)

For the work of June 2026

Contract number
BOG/2024/011
Etimad reference
2401780147
Contract
Board of Grievances headquarters, Riyadh — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
Board of Grievances Headquarters, Riyadh
Contract period
⁦2024-04-01⁩ — ⁦2027-06-30⁩
Original contract value
1,020,000,000
Current contract value
1,058,500,000including variations of SAR 38.5M

Certificate summary (SAR)

1Total value of work completed to date414,450,000
2Less: previous certificates(406,180,000)
3Value of work in this certificate8,270,000
4Less: retention (⁦10%⁩)(827,000)
5Less: advance payment recovery (⁦10%⁩)(827,000)
6Less: delay and breach penalties0
7Total deductions(1,654,000)
8Net before VAT6,616,000
9Add: value added tax (15%)992,400
10Net amount payable to the contractor7,608,400

Amount in words: Seven million six hundred eight thousand four hundred Saudi riyals only

Retention held up to this certificate: SAR 41.4M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation74,095,00065,769,0001,165,00066,934,000⁦90%⁩
Earthworks & foundations190,530,000102,554,0001,887,000104,441,000⁦55%⁩
Concrete & structural works328,135,000138,488,0002,839,000141,327,000⁦43%⁩
Mechanical, electrical & plumbing254,040,00068,042,0001,586,00069,628,000⁦27%⁩
Finishes & external works158,775,00027,291,000684,00027,975,000⁦18%⁩
Testing & commissioning52,925,0004,036,000109,0004,145,000⁦8%⁩
Total1,058,500,000406,180,0008,270,000414,450,000⁦39%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2026-07-05⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-07-07⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2026-07-10⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-07-13⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-07-16⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-07-05⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2026-07-07⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-07-10⁩

    Eng. Ahmed Y. Asiri · Director, Court Complexes

    Took 3 days

  4. Payment order prepared⁦2026-07-13⁩

    Khalid N. Al-Mutairi · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-07-16⁩

    Dr. Abdullah S. Al-Qahtani · President of the Board of Grievances

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Dr. Abdullah S. Al-Qahtani

Certificate history

16 July 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-07-16 13:00

13 July 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-07-13 13:00

10 July 2026

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2026-07-10 13:00

7 July 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-07-07 13:00

5 July 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-07-05 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close