Kingdom of Saudi Arabia
Board of Grievances
General Directorate of Financial Affairs — Contracts & Procurement
- Certificate no.
- 28
- Date
- 2026-10-07
- Hijri
- 26 Rabiʻ II 1448 AH
- Reference
- PAY-2026-015
Interim payment certificate no. (28)
For the work of September 2026
- Contract number
- BOG/2024/011
- Etimad reference
- 2401780147
- Contract
- Board of Grievances headquarters, Riyadh — construction
- Contractor
- Al-Bunyan Al-Rasekh Contracting Co.
- Contractor VAT number
- 310102487310003
- Project
- Board of Grievances Headquarters, Riyadh
- Contract period
- 2024-04-01 — 2027-06-30
- Original contract value
- 1,020,000,000
- Current contract value
- 1,058,500,000including variations of SAR 38.5M
Certificate summary (SAR)
| 1 | Total value of work completed to date | 453,000,000 |
| 2 | Less: previous certificates | (438,200,000) |
| 3 | Value of work in this certificate | 14,800,000 |
| 4 | Less: retention (10%) | (1,480,000) |
| 5 | Less: advance payment recovery (10%) | (1,480,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (2,960,000) |
| 8 | Net before VAT | 11,840,000 |
| 9 | Add: value added tax (15%) | 1,776,000 |
| 10 | Net amount payable to the contractor | 13,616,000 |
Amount in words: Thirteen million six hundred sixteen thousand Saudi riyals only
Retention held up to this certificate: SAR 45.3M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 74,095,000 | 71,116,000 | 2,043,000 | 73,159,000 | 99% |
| Earthworks & foundations | 190,530,000 | 110,825,000 | 3,331,000 | 114,156,000 | 60% |
| Concrete & structural works | 328,135,000 | 149,387,000 | 5,086,000 | 154,473,000 | 47% |
| Mechanical, electrical & plumbing | 254,040,000 | 73,219,000 | 2,885,000 | 76,104,000 | 30% |
| Finishes & external works | 158,775,000 | 29,323,000 | 1,255,000 | 30,578,000 | 19% |
| Testing & commissioning | 52,925,000 | 4,330,000 | 200,000 | 4,530,000 | 9% |
| Total | 1,058,500,000 | 438,200,000 | 14,800,000 | 453,000,000 | 43% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Hamad S. Al-Hajri
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Ahmed Y. Asiri
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani