Kingdom of Saudi Arabia
Board of Grievances
General Directorate of Financial Affairs — Contracts & Procurement
- Certificate no.
- 22
- Date
- 2026-03-29
- Hijri
- 10 Shawwal 1447 AH
- Reference
- PAY-2024-011-22
Interim payment certificate no. (22)
For the work of March 2026
- Contract number
- BOG/2024/011
- Etimad reference
- 2401780147
- Contract
- Board of Grievances headquarters, Riyadh — construction
- Contractor
- Al-Bunyan Al-Rasekh Contracting Co.
- Contractor VAT number
- 310102487310003
- Project
- Board of Grievances Headquarters, Riyadh
- Contract period
- 2024-04-01 — 2027-06-30
- Original contract value
- 1,020,000,000
- Current contract value
- 1,058,500,000including variations of SAR 38.5M
Certificate summary (SAR)
| 1 | Total value of work completed to date | 382,370,000 |
| 2 | Less: previous certificates | (369,310,000) |
| 3 | Value of work in this certificate | 13,060,000 |
| 4 | Less: retention (10%) | (1,306,000) |
| 5 | Less: advance payment recovery (10%) | (1,306,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (2,612,000) |
| 8 | Net before VAT | 10,448,000 |
| 9 | Add: value added tax (15%) | 1,567,200 |
| 10 | Net amount payable to the contractor | 12,015,200 |
Amount in words: Twelve million fifteen thousand two hundred Saudi riyals only
Retention held up to this certificate: SAR 38.2M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 74,095,000 | 59,886,000 | 1,867,000 | 61,753,000 | 83% |
| Earthworks & foundations | 190,530,000 | 93,344,000 | 3,013,000 | 96,357,000 | 51% |
| Concrete & structural works | 328,135,000 | 125,907,000 | 4,481,000 | 130,388,000 | 40% |
| Mechanical, electrical & plumbing | 254,040,000 | 61,765,000 | 2,473,000 | 64,238,000 | 25% |
| Finishes & external works | 158,775,000 | 24,750,000 | 1,060,000 | 25,810,000 | 16% |
| Testing & commissioning | 52,925,000 | 3,658,000 | 166,000 | 3,824,000 | 7% |
| Total | 1,058,500,000 | 369,310,000 | 13,060,000 | 382,370,000 | 36% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Hamad S. Al-Hajri
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Ahmed Y. Asiri
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani