Board of GrievancesMunjaz10My actionsNotifications

Certificate ⁦21⁩ — February 2026

Board of Grievances headquarters, Riyadh — construction

Kingdom of Saudi Arabia

Board of Grievances

General Directorate of Financial Affairs — Contracts & Procurement

Certificate no.
21
Date
⁦2026-02-25⁩
Hijri
8 Ramadan 1447 AH
Reference
PAY-2024-011-21

Interim payment certificate no. (⁦21⁩)

For the work of February 2026

Contract number
BOG/2024/011
Etimad reference
2401780147
Contract
Board of Grievances headquarters, Riyadh — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
Board of Grievances Headquarters, Riyadh
Contract period
⁦2024-04-01⁩ — ⁦2027-06-30⁩
Original contract value
1,020,000,000
Current contract value
1,058,500,000including variations of SAR 38.5M

Certificate summary (SAR)

1Total value of work completed to date369,310,000
2Less: previous certificates(352,070,000)
3Value of work in this certificate17,240,000
4Less: retention (⁦10%⁩)(1,724,000)
5Less: advance payment recovery (⁦10%⁩)(1,724,000)
6Less: delay and breach penalties0
7Total deductions(3,448,000)
8Net before VAT13,792,000
9Add: value added tax (15%)2,068,800
10Net amount payable to the contractor15,860,800

Amount in words: Fifteen million eight hundred sixty thousand eight hundred Saudi riyals only

Retention held up to this certificate: SAR 36.9M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation74,095,00057,165,0002,479,00059,644,000⁦80%⁩
Earthworks & foundations190,530,00089,072,0003,994,00093,066,000⁦49%⁩
Concrete & structural works328,135,000120,022,0005,913,000125,935,000⁦38%⁩
Mechanical, electrical & plumbing254,040,00058,797,0003,247,00062,044,000⁦24%⁩
Finishes & external works158,775,00023,539,0001,389,00024,928,000⁦16%⁩
Testing & commissioning52,925,0003,475,000218,0003,693,000⁦7%⁩
Total1,058,500,000352,070,00017,240,000369,310,000⁦35%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2026-02-25⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-02-27⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2026-03-02⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-03-05⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-03-08⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-02-25⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2026-02-27⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2026-03-02⁩

    Eng. Ahmed Y. Asiri · Director, Court Complexes

    Took 3 days

  4. Payment order prepared⁦2026-03-05⁩

    Khalid N. Al-Mutairi · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-03-08⁩

    Dr. Abdullah S. Al-Qahtani · President of the Board of Grievances

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Dr. Abdullah S. Al-Qahtani

Certificate history

8 March 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-03-08 13:00

5 March 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-03-05 13:00

2 March 2026

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2026-03-02 13:00

27 February 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-02-27 13:00

25 February 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-02-25 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close