Kingdom of Saudi Arabia
Board of Grievances
General Directorate of Financial Affairs — Contracts & Procurement
- Certificate no.
- 14
- Date
- 2025-07-12
- Hijri
- 17 Muharram 1447 AH
- Reference
- PAY-2024-011-14
Interim payment certificate no. (14)
For the work of June 2025
- Contract number
- BOG/2024/011
- Etimad reference
- 2401780147
- Contract
- Board of Grievances headquarters, Riyadh — construction
- Contractor
- Al-Bunyan Al-Rasekh Contracting Co.
- Contractor VAT number
- 310102487310003
- Project
- Board of Grievances Headquarters, Riyadh
- Contract period
- 2024-04-01 — 2027-06-30
- Original contract value
- 1,020,000,000
- Current contract value
- 1,058,500,000including variations of SAR 38.5M
Certificate summary (SAR)
| 1 | Total value of work completed to date | 231,580,000 |
| 2 | Less: previous certificates | (211,900,000) |
| 3 | Value of work in this certificate | 19,680,000 |
| 4 | Less: retention (10%) | (1,968,000) |
| 5 | Less: advance payment recovery (10%) | (1,968,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (3,936,000) |
| 8 | Net before VAT | 15,744,000 |
| 9 | Add: value added tax (15%) | 2,361,600 |
| 10 | Net amount payable to the contractor | 18,105,600 |
Amount in words: Eighteen million one hundred five thousand six hundred Saudi riyals only
Retention held up to this certificate: SAR 23.2M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 74,095,000 | 34,417,000 | 2,983,000 | 37,400,000 | 50% |
| Earthworks & foundations | 190,530,000 | 53,623,000 | 4,735,000 | 58,358,000 | 31% |
| Concrete & structural works | 328,135,000 | 72,236,000 | 6,733,000 | 78,969,000 | 24% |
| Mechanical, electrical & plumbing | 254,040,000 | 35,375,000 | 3,530,000 | 38,905,000 | 15% |
| Finishes & external works | 158,775,000 | 14,160,000 | 1,472,000 | 15,632,000 | 10% |
| Testing & commissioning | 52,925,000 | 2,089,000 | 227,000 | 2,316,000 | 4% |
| Total | 1,058,500,000 | 211,900,000 | 19,680,000 | 231,580,000 | 22% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Hamad S. Al-Hajri
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Ahmed Y. Asiri
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani