Kingdom of Saudi Arabia
Board of Grievances
General Directorate of Financial Affairs — Contracts & Procurement
- Certificate no.
- 19
- Date
- 2025-12-22
- Hijri
- 2 Rajab 1447 AH
- Reference
- PAY-2024-011-19
Interim payment certificate no. (19)
For the work of December 2025
- Contract number
- BOG/2024/011
- Etimad reference
- 2401780147
- Contract
- Board of Grievances headquarters, Riyadh — construction
- Contractor
- Al-Bunyan Al-Rasekh Contracting Co.
- Contractor VAT number
- 310102487310003
- Project
- Board of Grievances Headquarters, Riyadh
- Contract period
- 2024-04-01 — 2027-06-30
- Original contract value
- 1,020,000,000
- Current contract value
- 1,058,500,000including variations of SAR 38.5M
Certificate summary (SAR)
| 1 | Total value of work completed to date | 335,200,000 |
| 2 | Less: previous certificates | (317,560,000) |
| 3 | Value of work in this certificate | 17,640,000 |
| 4 | Less: retention (10%) | (1,764,000) |
| 5 | Less: advance payment recovery (10%) | (1,764,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (3,528,000) |
| 8 | Net before VAT | 14,112,000 |
| 9 | Add: value added tax (15%) | 2,116,800 |
| 10 | Net amount payable to the contractor | 16,228,800 |
Amount in words: Sixteen million two hundred twenty-eight thousand eight hundred Saudi riyals only
Retention held up to this certificate: SAR 33.5M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 74,095,000 | 51,561,000 | 2,574,000 | 54,135,000 | 73% |
| Earthworks & foundations | 190,530,000 | 80,341,000 | 4,129,000 | 84,470,000 | 44% |
| Concrete & structural works | 328,135,000 | 108,257,000 | 6,046,000 | 114,303,000 | 35% |
| Mechanical, electrical & plumbing | 254,040,000 | 53,034,000 | 3,280,000 | 56,314,000 | 22% |
| Finishes & external works | 158,775,000 | 21,232,000 | 1,394,000 | 22,626,000 | 14% |
| Testing & commissioning | 52,925,000 | 3,135,000 | 217,000 | 3,352,000 | 6% |
| Total | 1,058,500,000 | 317,560,000 | 17,640,000 | 335,200,000 | 32% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Hamad S. Al-Hajri
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Ahmed Y. Asiri
Finance & contracts
Khalid N. Al-Mutairi
Authority holder
Dr. Abdullah S. Al-Qahtani