Board of GrievancesMunjaz10My actionsNotifications

Certificate ⁦17⁩ — September 2025

Board of Grievances headquarters, Riyadh — construction

Kingdom of Saudi Arabia

Board of Grievances

General Directorate of Financial Affairs — Contracts & Procurement

Certificate no.
17
Date
⁦2025-10-18⁩
Hijri
26 Rabiʻ II 1447 AH
Reference
PAY-2024-011-17

Interim payment certificate no. (⁦17⁩)

For the work of September 2025

Contract number
BOG/2024/011
Etimad reference
2401780147
Contract
Board of Grievances headquarters, Riyadh — construction
Contractor
Al-Bunyan Al-Rasekh Contracting Co.
Contractor VAT number
310102487310003
Project
Board of Grievances Headquarters, Riyadh
Contract period
⁦2024-04-01⁩ — ⁦2027-06-30⁩
Original contract value
1,020,000,000
Current contract value
1,058,500,000including variations of SAR 38.5M

Certificate summary (SAR)

1Total value of work completed to date295,690,000
2Less: previous certificates(276,730,000)
3Value of work in this certificate18,960,000
4Less: retention (⁦10%⁩)(1,896,000)
5Less: advance payment recovery (⁦10%⁩)(1,896,000)
6Less: delay and breach penalties0
7Total deductions(3,792,000)
8Net before VAT15,168,000
9Add: value added tax (15%)2,275,200
10Net amount payable to the contractor17,443,200

Amount in words: Seventeen million four hundred forty-three thousand two hundred Saudi riyals only

Retention held up to this certificate: SAR 29.6M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation74,095,00044,944,0002,810,00047,754,000⁦64%⁩
Earthworks & foundations190,530,00070,026,0004,488,00074,514,000⁦39%⁩
Concrete & structural works328,135,00094,336,0006,494,000100,830,000⁦31%⁩
Mechanical, electrical & plumbing254,040,00046,200,0003,476,00049,676,000⁦20%⁩
Finishes & external works158,775,00018,493,0001,466,00019,959,000⁦13%⁩
Testing & commissioning52,925,0002,731,000226,0002,957,000⁦6%⁩
Total1,058,500,000276,730,00018,960,000295,690,000⁦28%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Hamad S. Al-Hajri

Al-Hajri⁦2025-10-18⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2025-10-20⁩

Project manager

Eng. Ahmed Y. Asiri

Asiri⁦2025-10-23⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-10-26⁩

Authority holder

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2025-10-29⁩
Issued electronically through Munjaz Integration-ready for Etimad

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-10-18⁩

    Eng. Hamad S. Al-Hajri

  2. Engineer verifies quantities⁦2025-10-20⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision

    Took 2 days

  3. Project manager certifies⁦2025-10-23⁩

    Eng. Ahmed Y. Asiri · Director, Court Complexes

    Took 3 days

  4. Payment order prepared⁦2025-10-26⁩

    Khalid N. Al-Mutairi · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-10-29⁩

    Dr. Abdullah S. Al-Qahtani · President of the Board of Grievances

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Ahmed Y. Asiri → Dr. Abdullah S. Al-Qahtani

Certificate history

29 October 2025

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2025-10-29 13:00

26 October 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-10-26 13:00

23 October 2025

  1. Approval: Eng. Ahmed Y. Asiri signed “Project manager certifies”

    2025-10-23 13:00

20 October 2025

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2025-10-20 13:00

18 October 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-10-18 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close