RSK-0021
Main contractor cash-flow distress and unpaid subcontractors
East Waha Wastewater Treatment Plant Financial 25 Critical SAR 36M Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Utilities & Public Services P-021 · w.aljuhani@alwaha.gov.sa Escalate Escalated In 8 days 2026-11-05 · 25 Jumada I 1448 AH 1 d RSK-0015
Steel and asphalt price rises driving price-adjustment claims
Northern Ring Road Development — Phase 2 Financial 20 Critical SAR 48M Eng. Ahmed Y. Asiri Eng. Ahmed Y. Asiri Director General, Roads & Bridges P-020 · a.asiri@alwaha.gov.sa Escalate Escalated In 18 days 2026-11-15 · 5 Jumada II 1448 AH 4 d RSK-0016
Late land acquisition and utility diversions in sections 3 and 4
Northern Ring Road Development — Phase 2 Schedule 20 Critical SAR 31M Eng. Bandar M. Al-Shammari Eng. Bandar M. Al-Shammari Deputy, Infrastructure P-013 · b.alshammari@alwaha.gov.sa Escalate Escalated In 64 days 2026-12-31 · 22 Rajab 1448 AH 4 d RSK-0026
Contractor financial claims piling up over unapproved variations
Government Offices Complex Financial 20 Critical SAR 41M Eng. Shahad M. Al-Malki Eng. Shahad M. Al-Malki Director, Government Buildings & Facilities P-022 · s.almalki@alwaha.gov.sa Escalate Escalated In 13 days 2026-11-10 · 30 Jumada I 1448 AH 3 d RSK-0034
Unforeseen ground conditions at the pier foundations in the wadi bed
Wadi Al-Rummah Bridge Technical 20 Critical SAR 27M Eng. Ahmed Y. Asiri Eng. Ahmed Y. Asiri Director General, Roads & Bridges P-020 · a.asiri@alwaha.gov.sa Escalate Escalated In 23 days 2026-11-20 · 10 Jumada II 1448 AH 5 d RSK-0044
Late land handover and title deed from the owning entity
Regional Emergency & Safety Centre Regulatory 20 Critical SAR 12M Eng. Shahad M. Al-Malki Eng. Shahad M. Al-Malki Director, Government Buildings & Facilities P-022 · s.almalki@alwaha.gov.sa Escalate Escalated In 64 days 2026-12-31 · 22 Rajab 1448 AH 22 d RSK-0001
Nafath and SADAD integration interfaces not ready on time
Unified Digital Services Platform Technical 16 High SAR 2.4M Eng. Sultan F. Al-Ghamdi Eng. Sultan F. Al-Ghamdi Project Manager, Unified Digital Services Platform P-005 · s.alghamdi@alwaha.gov.sa Mitigate Open In 18 days 2026-11-15 · 5 Jumada II 1448 AH 2 d RSK-0002
Shortage of integration and back-end engineers on the vendor team
Unified Digital Services Platform Resource 16 High SAR 1.9M Eng. Sultan F. Al-Ghamdi Eng. Sultan F. Al-Ghamdi Project Manager, Unified Digital Services Platform P-005 · s.alghamdi@alwaha.gov.sa Escalate Escalated In 8 days 2026-11-05 · 25 Jumada I 1448 AH 2 d RSK-0012
Customisation and Etimad integration costs exceeding the approved contingency
Enterprise Resource Planning (ERP) System Financial 16 High SAR 6.8M Dana S. Al-Saleh Dana S. Al-Saleh Director, Enterprise Applications P-025 · d.alsaleh@alwaha.gov.sa Escalate Escalated In 13 days 2026-11-10 · 30 Jumada I 1448 AH 5 d RSK-0017
Contractor claim for a 120-day extension with compensation
Northern Ring Road Development — Phase 2 Contractual 16 High SAR 18.5M Khalid N. Al-Mutairi Khalid N. Al-Mutairi Senior Finance & Contracts Specialist P-007 · k.almutairi@alwaha.gov.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 8 d RSK-0019
Exchange-rate swings on imported equipment without fixed prices
National Backup Data Centre Financial 16 High SAR 7.4M Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@alwaha.gov.sa Mitigate Open In 23 days 2026-11-20 · 10 Jumada II 1448 AH 7 d RSK-0024
Marine protection costs up after the hydrographic survey
Waterfront Rehabilitation Financial 16 High SAR 22.5M Eng. Fahad T. Al-Sulami Eng. Fahad T. Al-Sulami Director, Urban Development P-023 · f.alsulami@alwaha.gov.sa Escalate Escalated In 15 days 2026-11-12 · 2 Jumada II 1448 AH 6 d RSK-0027
Late delivery of curtain-wall glazing from the overseas factory
Government Offices Complex Schedule 16 High SAR 15M Eng. Shahad M. Al-Malki Eng. Shahad M. Al-Malki Director, Government Buildings & Facilities P-022 · s.almalki@alwaha.gov.sa Mitigate Open In 48 days 2026-12-15 · 6 Rajab 1448 AH 3 d RSK-0036
Logistics developer late on its infrastructure investment share
Northern Logistics Zone Infrastructure Financial 16 High SAR 14M Yousef A. Al-Omari Yousef A. Al-Omari Deputy, Investment & Economic Development P-016 · y.alomari@alwaha.gov.sa Mitigate Open In 64 days 2026-12-31 · 22 Rajab 1448 AH 56 d RSK-0043
Funding left out of the 2027 budget, keeping the tender suspended
Energy Retrofit of Existing Buildings (ESCO) Financial 16 High SAR 4.8M Eng. Mishari K. Al-Otaibi Eng. Mishari K. Al-Otaibi Director, Sustainability & Environment P-028 · m.alotaibi@alwaha.gov.sa Escalate Escalated In 48 days 2026-12-15 · 6 Rajab 1448 AH 20 d RSK-0022
Treated-water quality failing NCEC requirements
East Waha Wastewater Treatment Plant Regulatory 15 High SAR 12M Eng. Mishari K. Al-Otaibi Eng. Mishari K. Al-Otaibi Director, Sustainability & Environment P-028 · m.alotaibi@alwaha.gov.sa Mitigate Open In 79 days 2027-01-15 · 7 Shaʻban 1448 AH 9 d RSK-0028
Possible removal of the MEP subcontractor
Government Offices Complex Contractual 15 High SAR 9.5M Eng. Abdulrahman S. Al-Harbi Eng. Abdulrahman S. Al-Harbi Deputy, Capital Projects P-014 · ab.alharbi@alwaha.gov.sa Mitigate Open In 28 days 2026-11-25 · 15 Jumada II 1448 AH 10 d RSK-0046
Tender prices 18% above the engineer’s estimate
Abha – Al-Baha Road Dualisation Financial 15 High SAR 93.6M Eng. Ibrahim A. Al-Ghamdi Eng. Ibrahim A. Al-Ghamdi Director, Engineering Supervision P-036 · i.alghamdi@alwaha.gov.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 5 d RSK-0003
Late sign-off of licensing-service requirements by the owning departments
Unified Digital Services Platform Stakeholder 12 Medium SAR 1.2M Eng. Reem K. Al-Dosari Eng. Reem K. Al-Dosari Programme Manager, Digital Government Services P-004 · r.aldosari@alwaha.gov.sa Mitigate Open In 23 days 2026-11-20 · 10 Jumada II 1448 AH 6 d RSK-0006
Possible critical findings in the pre-launch penetration test
Unified Digital Services Platform Security 12 Medium SAR 600K Eng. Yasser M. Al-Zahrani Eng. Yasser M. Al-Zahrani Director, Cybersecurity P-026 · y.alzahrani@alwaha.gov.sa Mitigate Open In 74 days 2027-01-10 · 2 Shaʻban 1448 AH 8 d RSK-0013
Late migration and reconciliation of historical financial data
Enterprise Resource Planning (ERP) System Schedule 12 Medium SAR 2.1M Dana S. Al-Saleh Dana S. Al-Saleh Director, Enterprise Applications P-025 · d.alsaleh@alwaha.gov.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 5 d RSK-0020
Late delivery of cooling units and standby generators
National Backup Data Centre Schedule 12 Medium SAR 3.2M Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@alwaha.gov.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 7 d RSK-0023
Failures in the main force mains during commissioning
East Waha Wastewater Treatment Plant Technical 12 Medium SAR 5.6M Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Utilities & Public Services P-021 · w.aljuhani@alwaha.gov.sa Mitigate Open In 53 days 2026-12-20 · 11 Rajab 1448 AH 9 d RSK-0025
Late marine-works permits from the competent authorities
Waterfront Rehabilitation Regulatory 12 Medium SAR 6M Eng. Fahad T. Al-Sulami Eng. Fahad T. Al-Sulami Director, Urban Development P-023 · f.alsulami@alwaha.gov.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 6 d RSK-0031
Late integration of the central control system with the lights
Smart Street Lighting Technical 12 Medium SAR 1.4M Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Utilities & Public Services P-021 · w.aljuhani@alwaha.gov.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 44 d RSK-0033
Municipal objections to trenching in built-up districts
Fibre Optic Network Expansion Stakeholder 12 Medium SAR 2.2M Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@alwaha.gov.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 37 d RSK-0035
Pile lengths exceeding contract quantities
Wadi Al-Rummah Bridge Cost 12 Medium SAR 8.4M Eng. Ahmed Y. Asiri Eng. Ahmed Y. Asiri Director General, Roads & Bridges P-020 · a.asiri@alwaha.gov.sa Mitigate Open In 48 days 2026-12-15 · 6 Rajab 1448 AH 5 d RSK-0018
Safety incidents in traffic diversion zones
Northern Ring Road Development — Phase 2 Technical 10 Medium SAR 4M Eng. Ahmed Y. Asiri Eng. Ahmed Y. Asiri Director General, Roads & Bridges P-020 · a.asiri@alwaha.gov.sa Mitigate In progress In 245 days 2027-06-30 · 25 Muharram 1449 AH 14 d RSK-0042
Undetected vulnerabilities in legacy systems before SOC onboarding
Enterprise Cybersecurity Programme Security 10 Medium SAR 3M Eng. Yasser M. Al-Zahrani Eng. Yasser M. Al-Zahrani Director, Cybersecurity P-026 · y.alzahrani@alwaha.gov.sa Mitigate In progress In 34 days 2026-12-01 · 21 Jumada II 1448 AH 2 d RSK-0005
Incomplete migration of beneficiary data from legacy systems
Unified Digital Services Platform Technical 9 Medium SAR 750K Rakan F. Al-Mohammadi Rakan F. Al-Mohammadi Data Engineer P-032 · r.almohammadi@alwaha.gov.sa Mitigate Open In 34 days 2026-12-01 · 21 Jumada II 1448 AH 7 d RSK-0007
Staff resistance to the new digital procedures
Unified Digital Services Platform Stakeholder 9 Medium SAR 300K Nouf M. Al-Balawi Nouf M. Al-Balawi Change Management Specialist P-035 · n.albalawi@alwaha.gov.sa Mitigate In progress In 110 days 2027-02-15 · 8 Ramadan 1448 AH 13 d RSK-0010
Mobile-app team competing with the platform for the same people
Unified Digital Services Platform Resource 9 Medium SAR 520K Eng. Reem K. Al-Dosari Eng. Reem K. Al-Dosari Programme Manager, Digital Government Services P-004 · r.aldosari@alwaha.gov.sa Mitigate Open In 21 days 2026-11-18 · 8 Jumada II 1448 AH 3 d RSK-0048
Cloud hosting contract signed late
Unified Digital Services Platform Contractual 9 Medium — Khalid N. Al-Mutairi Khalid N. Al-Mutairi Senior Finance & Contracts Specialist P-007 · k.almutairi@alwaha.gov.sa Accept Closed 2025-07-01 2025-07-01 · 6 Muharram 1447 AH 479 d RSK-0014
Implementation consultants’ contracts ending before go-live
Enterprise Resource Planning (ERP) System Resource 9 Medium SAR 900K Munirah A. Al-Khalidi Munirah A. Al-Khalidi Deputy, Financial Affairs P-018 · m.alkhalidi@alwaha.gov.sa Mitigate Open In 48 days 2026-12-15 · 6 Rajab 1448 AH 12 d RSK-0029
Cloud consumption costs above estimate
Migration to the Government Cloud Financial 9 Medium SAR 2.6M Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@alwaha.gov.sa Mitigate Open In 64 days 2026-12-31 · 22 Rajab 1448 AH 11 d RSK-0030
Lighting-pole quantity variances between drawings and site
Smart Street Lighting Financial 9 Medium SAR 1.8M Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Utilities & Public Services P-021 · w.aljuhani@alwaha.gov.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 44 d RSK-0032
Higher reinstatement costs after trenching
Fibre Optic Network Expansion Financial 9 Medium SAR 3.9M Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@alwaha.gov.sa Mitigate Open In 64 days 2026-12-31 · 22 Rajab 1448 AH 37 d RSK-0037
Too few accredited data owners in the departments
Data Governance & Master Data Management Resource 9 Medium SAR 650K Rahaf I. Al-Nefaie Rahaf I. Al-Nefaie Director, Data & AI P-027 · r.alnefaie@alwaha.gov.sa Mitigate Open In 34 days 2026-12-01 · 21 Jumada II 1448 AH 8 d RSK-0038
High UAT defect count in the outgoing-mail module
Document & Correspondence Management Platform Technical 9 Medium SAR 480K Dana S. Al-Saleh Dana S. Al-Saleh Director, Enterprise Applications P-025 · d.alsaleh@alwaha.gov.sa Mitigate Open In 13 days 2026-11-10 · 30 Jumada I 1448 AH 7 d RSK-0039
Late supply of mature trees from approved nurseries
Al-Waha Central Park Schedule 9 Medium SAR 2.1M Eng. Fahad T. Al-Sulami Eng. Fahad T. Al-Sulami Director, Urban Development P-023 · f.alsulami@alwaha.gov.sa Mitigate Open In 64 days 2026-12-31 · 22 Rajab 1448 AH 4 d RSK-0040
Low middle-management participation in change activities
Change Management & Culture Programme Stakeholder 9 Medium SAR 250K Ghada A. Al-Shahrani Ghada A. Al-Shahrani Director, Organisational Excellence P-029 · g.alshahrani@alwaha.gov.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 34 d RSK-0047
Camera-data privacy requirements under the Personal Data Protection Law
Intelligent Traffic Monitoring System Regulatory 9 Medium SAR 900K Eng. Yasser M. Al-Zahrani Eng. Yasser M. Al-Zahrani Director, Cybersecurity P-026 · y.alzahrani@alwaha.gov.sa Mitigate Open In 95 days 2027-01-31 · 23 Shaʻban 1448 AH 10 d RSK-0004
Cloud hosting capacity exceeded at launch
Unified Digital Services Platform Technical 8 Medium SAR 900K Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@alwaha.gov.sa Mitigate In progress In 48 days 2026-12-15 · 6 Rajab 1448 AH 9 d RSK-0008
Late delivery of identity & access management licences
Unified Digital Services Platform Contractual 6 Low SAR 450K Khalid N. Al-Mutairi Khalid N. Al-Mutairi Senior Finance & Contracts Specialist P-007 · k.almutairi@alwaha.gov.sa Transfer Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 10 d RSK-0011
Updated user-experience standards from the Digital Government Authority
Unified Digital Services Platform Regulatory 6 Low SAR 280K Lama S. Al-Harbi Lama S. Al-Harbi Senior Business Analyst P-006 · l.alharbi@alwaha.gov.sa Accept Open In 95 days 2027-01-31 · 23 Shaʻban 1448 AH 16 d RSK-0045
Preliminary-handover snags on the outlet gates
Rainwater Harvesting & Small Dams Technical 6 Low SAR 600K Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Utilities & Public Services P-021 · w.aljuhani@alwaha.gov.sa Mitigate Open In 15 days 2026-11-12 · 2 Jumada II 1448 AH 2 d