Subject: Financial claim for variation 7
The VP, Projects & Infrastructure, Al-Waha Region Development Authority
Greetings,
We submit a financial claim of SAR 14,200,000 for the additional works arising from variation 7 — the operational requirements added after concept design approval — together with a request for a 150-day extension of time.
The bill of quantities and the time-impact analysis are attached; we ask that the claim be considered under the contract.
With our kind regards,
Managing Director, Gulf General Contracting Co.
Eng. Sami Al-Dakheel
Priced bill of quantities · Time-impact analysis · Claims file