Legal opinion on referring the claims to dispute resolution

CompletedConfidential

Internal Response, dated 30 Rabiʻ II 1448 AH

Kingdom of Saudi Arabia

Al-Waha Region Development Authority

Legal Department

Number:
م/1448/0415
Date:
⁦30⁩ Rabiʻ II ⁦1448⁩ AH
Corresponding to:
⁦11⁩ October ⁦2026⁩
Attachments:
0

CONFIDENTIAL

Subject: Legal opinion on referring the claims to dispute resolution

The Director, Enterprise PMO

Greetings,

Having studied Gulf General Contracting’s claim for variation ⁦7⁩, Legal finds disputed items on the scope of the design-build contract and recommends referral to the dispute-resolution committee under Article ⁦86⁩, while keeping delay penalties on work unrelated to the change.

With our kind regards,

Director, Legal Department

Hisham Al-Qahtani