RSK-0021
Main contractor cash-flow distress and unpaid subcontractors
Dammam Administrative Courts Complex — Rehabilitation & Extension Financial 25 Critical SAR 36M Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Facilities Operations & Maintenance P-021 · w.aljuhani@bog.gov.sa Escalate Escalated In 8 days 2026-11-05 · 25 Jumada I 1448 AH 1 d RSK-0015
Steel and concrete price rises driving price-adjustment claims
Board of Grievances Headquarters, Riyadh Financial 20 Critical SAR 48M Eng. Ahmed Y. Asiri Eng. Ahmed Y. Asiri Director, Court Complexes P-020 · a.asiri@bog.gov.sa Escalate Escalated In 18 days 2026-11-15 · 5 Jumada II 1448 AH 4 d RSK-0016
Late handover of the northern plot and utility diversions in zones 3 and 4
Board of Grievances Headquarters, Riyadh Schedule 20 Critical SAR 31M Eng. Bandar M. Al-Shammari Eng. Bandar M. Al-Shammari Director General, Judicial Facilities P-013 · b.alshammari@bog.gov.sa Escalate Escalated In 64 days 2026-12-31 · 22 Rajab 1448 AH 4 d RSK-0026
Contractor financial claims piling up over unapproved variations
Riyadh Administrative Court Building Financial 20 Critical SAR 41M Eng. Shahad M. Al-Malki Eng. Shahad M. Al-Malki Director, Judicial Buildings & Premises P-022 · s.almalki@bog.gov.sa Escalate Escalated In 13 days 2026-11-10 · 30 Jumada I 1448 AH 3 d RSK-0034
Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16
Buraydah Administrative Courts Complex Technical 20 Critical SAR 27M Eng. Ahmed Y. Asiri Eng. Ahmed Y. Asiri Director, Court Complexes P-020 · a.asiri@bog.gov.sa Escalate Escalated In 23 days 2026-11-20 · 10 Jumada II 1448 AH 5 d RSK-0044
Late land handover and title deed from the owning entity in Wadi Al-Dawasir
Digital Administrative Court HQ, Wadi Al-Dawasir Regulatory 20 Critical SAR 12M Eng. Shahad M. Al-Malki Eng. Shahad M. Al-Malki Director, Judicial Buildings & Premises P-022 · s.almalki@bog.gov.sa Escalate Escalated In 64 days 2026-12-31 · 22 Rajab 1448 AH 22 d RSK-0001
Nafath and Government Service Bus integration interfaces not ready on time
Mueen Digital Platform — Release 4 Technical 16 High SAR 2.4M Eng. Sultan F. Al-Ghamdi Eng. Sultan F. Al-Ghamdi Project Manager, Mueen Platform — Release 4 P-005 · s.alghamdi@bog.gov.sa Mitigate Open In 18 days 2026-11-15 · 5 Jumada II 1448 AH 2 d RSK-0002
Shortage of integration and back-end engineers on the vendor team
Mueen Digital Platform — Release 4 Resource 16 High SAR 1.9M Eng. Sultan F. Al-Ghamdi Eng. Sultan F. Al-Ghamdi Project Manager, Mueen Platform — Release 4 P-005 · s.alghamdi@bog.gov.sa Escalate Escalated In 8 days 2026-11-05 · 25 Jumada I 1448 AH 2 d RSK-0012
Customisation and Etimad integration costs exceeding the approved contingency
Board ERP System Financial 16 High SAR 6.8M Dana S. Al-Saleh Dana S. Al-Saleh Director, Systems & Applications P-025 · d.alsaleh@bog.gov.sa Escalate Escalated In 13 days 2026-11-10 · 30 Jumada I 1448 AH 5 d RSK-0017
Contractor claim for a 120-day extension with compensation
Board of Grievances Headquarters, Riyadh Contractual 16 High SAR 18.5M Khalid N. Al-Mutairi Khalid N. Al-Mutairi Senior Finance & Contracts Specialist P-007 · k.almutairi@bog.gov.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 8 d RSK-0019
Exchange-rate swings on imported equipment without fixed prices
Board Backup Data Centre Financial 16 High SAR 7.4M Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@bog.gov.sa Mitigate Open In 23 days 2026-11-20 · 10 Jumada II 1448 AH 7 d RSK-0024
Ground-improvement costs up after the geotechnical survey
Jeddah Administrative Courts Complex Financial 16 High SAR 22.5M Eng. Fahad T. Al-Sulami Eng. Fahad T. Al-Sulami Director, Design & Fit-out P-023 · f.alsulami@bog.gov.sa Escalate Escalated In 15 days 2026-11-12 · 2 Jumada II 1448 AH 6 d RSK-0027
Late delivery of curtain-wall glazing from the overseas factory
Riyadh Administrative Court Building Schedule 16 High SAR 15M Eng. Shahad M. Al-Malki Eng. Shahad M. Al-Malki Director, Judicial Buildings & Premises P-022 · s.almalki@bog.gov.sa Mitigate Open In 48 days 2026-12-15 · 6 Rajab 1448 AH 3 d RSK-0036
Municipality late bringing utilities and access roads to the site
Arar Administrative Courts Complex Financial 16 High SAR 14M Yousef A. Al-Omari Yousef A. Al-Omari Director General, Partnerships & Revenue Development P-016 · y.alomari@bog.gov.sa Mitigate Open In 64 days 2026-12-31 · 22 Rajab 1448 AH 56 d RSK-0043
Funding left out of the 2027 budget, keeping the tender suspended
Energy Retrofit of Existing Court Buildings (ESCO) Financial 16 High SAR 4.8M Eng. Mishari K. Al-Otaibi Eng. Mishari K. Al-Otaibi Director, Sustainability & Energy Efficiency P-028 · m.alotaibi@bog.gov.sa Escalate Escalated In 48 days 2026-12-15 · 6 Rajab 1448 AH 20 d RSK-0022
Fire-fighting and evacuation systems failing Civil Defence requirements
Dammam Administrative Courts Complex — Rehabilitation & Extension Regulatory 15 High SAR 12M Eng. Mishari K. Al-Otaibi Eng. Mishari K. Al-Otaibi Director, Sustainability & Energy Efficiency P-028 · m.alotaibi@bog.gov.sa Mitigate Open In 79 days 2027-01-15 · 7 Shaʻban 1448 AH 9 d RSK-0028
Possible removal of the MEP subcontractor
Riyadh Administrative Court Building Contractual 15 High SAR 9.5M Eng. Abdulrahman S. Al-Harbi Eng. Abdulrahman S. Al-Harbi Director General, Engineering Projects P-014 · ab.alharbi@bog.gov.sa Mitigate Open In 28 days 2026-11-25 · 15 Jumada II 1448 AH 10 d RSK-0046
Tender prices 18% above the engineer’s estimate
Asir Administrative Court of Appeal Complex Financial 15 High SAR 93.6M Eng. Ibrahim A. Al-Ghamdi Eng. Ibrahim A. Al-Ghamdi Director, Engineering Supervision P-036 · i.alghamdi@bog.gov.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 5 d RSK-0003
Late sign-off of case-registration requirements by the owning courts
Mueen Digital Platform — Release 4 Stakeholder 12 Medium SAR 1.2M Eng. Reem K. Al-Dosari Eng. Reem K. Al-Dosari Head of the Mueen Platform Office & Digital Judicial Services Programme Manager P-004 · r.aldosari@bog.gov.sa Mitigate Open In 23 days 2026-11-20 · 10 Jumada II 1448 AH 6 d RSK-0006
Possible critical findings in the pre-launch penetration test
Mueen Digital Platform — Release 4 Security 12 Medium SAR 600K Eng. Yasser M. Al-Zahrani Eng. Yasser M. Al-Zahrani Director, Cybersecurity P-026 · y.alzahrani@bog.gov.sa Mitigate Open In 74 days 2027-01-10 · 2 Shaʻban 1448 AH 8 d RSK-0013
Late migration and reconciliation of historical financial data
Board ERP System Schedule 12 Medium SAR 2.1M Dana S. Al-Saleh Dana S. Al-Saleh Director, Systems & Applications P-025 · d.alsaleh@bog.gov.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 5 d RSK-0020
Late delivery of cooling units and standby generators
Board Backup Data Centre Schedule 12 Medium SAR 3.2M Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@bog.gov.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 7 d RSK-0023
Central HVAC failures during commissioning
Dammam Administrative Courts Complex — Rehabilitation & Extension Technical 12 Medium SAR 5.6M Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Facilities Operations & Maintenance P-021 · w.aljuhani@bog.gov.sa Mitigate Open In 53 days 2026-12-20 · 11 Rajab 1448 AH 9 d RSK-0025
Late building permits from the Jeddah municipality
Jeddah Administrative Courts Complex Regulatory 12 Medium SAR 6M Eng. Fahad T. Al-Sulami Eng. Fahad T. Al-Sulami Director, Design & Fit-out P-023 · f.alsulami@bog.gov.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 6 d RSK-0031
Late integration of the central monitoring room with building systems
Smart Security & Access for Court Buildings Technical 12 Medium SAR 1.4M Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Facilities Operations & Maintenance P-021 · w.aljuhani@bog.gov.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 44 d RSK-0033
Municipal objections to trenching in built-up districts
Secure Judicial Network Stakeholder 12 Medium SAR 2.2M Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@bog.gov.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 37 d RSK-0035
Pile lengths exceeding contract quantities
Buraydah Administrative Courts Complex Cost 12 Medium SAR 8.4M Eng. Ahmed Y. Asiri Eng. Ahmed Y. Asiri Director, Court Complexes P-020 · a.asiri@bog.gov.sa Mitigate Open In 48 days 2026-12-15 · 6 Rajab 1448 AH 5 d RSK-0018
Safety incidents around cranes and deep excavations
Board of Grievances Headquarters, Riyadh Technical 10 Medium SAR 4M Eng. Ahmed Y. Asiri Eng. Ahmed Y. Asiri Director, Court Complexes P-020 · a.asiri@bog.gov.sa Mitigate In progress In 245 days 2027-06-30 · 25 Muharram 1449 AH 14 d RSK-0042
Undetected vulnerabilities in legacy systems before SOC onboarding
Board Cybersecurity Programme Security 10 Medium SAR 3M Eng. Yasser M. Al-Zahrani Eng. Yasser M. Al-Zahrani Director, Cybersecurity P-026 · y.alzahrani@bog.gov.sa Mitigate In progress In 34 days 2026-12-01 · 21 Jumada II 1448 AH 2 d RSK-0005
Incomplete migration of pending-case data from legacy systems
Mueen Digital Platform — Release 4 Technical 9 Medium SAR 750K Rakan F. Al-Mohammadi Rakan F. Al-Mohammadi Data Engineer P-032 · r.almohammadi@bog.gov.sa Mitigate Open In 34 days 2026-12-01 · 21 Jumada II 1448 AH 7 d RSK-0007
Clerks and circuit staff resisting the new digital procedures
Mueen Digital Platform — Release 4 Stakeholder 9 Medium SAR 300K Nouf M. Al-Balawi Nouf M. Al-Balawi Change Management Specialist P-035 · n.albalawi@bog.gov.sa Mitigate In progress In 110 days 2027-02-15 · 8 Ramadan 1448 AH 13 d RSK-0010
Mobile-app team competing with the platform for the same people
Mueen Digital Platform — Release 4 Resource 9 Medium SAR 520K Eng. Reem K. Al-Dosari Eng. Reem K. Al-Dosari Head of the Mueen Platform Office & Digital Judicial Services Programme Manager P-004 · r.aldosari@bog.gov.sa Mitigate Open In 21 days 2026-11-18 · 8 Jumada II 1448 AH 3 d RSK-0048
Cloud hosting contract signed late
Mueen Digital Platform — Release 4 Contractual 9 Medium — Khalid N. Al-Mutairi Khalid N. Al-Mutairi Senior Finance & Contracts Specialist P-007 · k.almutairi@bog.gov.sa Accept Closed 2025-07-01 2025-07-01 · 6 Muharram 1447 AH 479 d RSK-0014
Implementation consultants’ contracts ending before go-live
Board ERP System Resource 9 Medium SAR 900K Munirah A. Al-Khalidi Munirah A. Al-Khalidi Director General, Financial Affairs P-018 · m.alkhalidi@bog.gov.sa Mitigate Open In 48 days 2026-12-15 · 6 Rajab 1448 AH 12 d RSK-0029
Cloud consumption costs above estimate
Judicial Systems Migration to the Government Cloud Financial 9 Medium SAR 2.6M Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@bog.gov.sa Mitigate Open In 64 days 2026-12-31 · 22 Rajab 1448 AH 11 d RSK-0030
Camera and gate quantity variances between drawings and site
Smart Security & Access for Court Buildings Financial 9 Medium SAR 1.8M Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Facilities Operations & Maintenance P-021 · w.aljuhani@bog.gov.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 44 d RSK-0032
Higher reinstatement costs after network trenching
Secure Judicial Network Financial 9 Medium SAR 3.9M Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@bog.gov.sa Mitigate Open In 64 days 2026-12-31 · 22 Rajab 1448 AH 37 d RSK-0037
Too few accredited data owners in the courts and departments
Judicial Data Governance & Master Data Resource 9 Medium SAR 650K Rahaf I. Al-Nefaie Rahaf I. Al-Nefaie Head, AI & Emerging Technologies Office P-027 · r.alnefaie@bog.gov.sa Mitigate Open In 34 days 2026-12-01 · 21 Jumada II 1448 AH 8 d RSK-0038
High UAT defect count in the outgoing-mail module
Administrative Correspondence & e-Archive Platform Technical 9 Medium SAR 480K Dana S. Al-Saleh Dana S. Al-Saleh Director, Systems & Applications P-025 · d.alsaleh@bog.gov.sa Mitigate Open In 13 days 2026-11-10 · 30 Jumada I 1448 AH 7 d RSK-0039
Late supply of courtroom audio-visual systems
Hail Administrative Court Building Schedule 9 Medium SAR 2.1M Eng. Fahad T. Al-Sulami Eng. Fahad T. Al-Sulami Director, Design & Fit-out P-023 · f.alsulami@bog.gov.sa Mitigate Open In 64 days 2026-12-31 · 22 Rajab 1448 AH 4 d RSK-0040
Low participation of circuit heads in change activities
Change Management for the Digital Judiciary Stakeholder 9 Medium SAR 250K Ghada A. Al-Shahrani Ghada A. Al-Shahrani Director, Organisational Excellence P-029 · g.alshahrani@bog.gov.sa Mitigate Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 34 d RSK-0047
Privacy requirements for video-hearing recordings under the Personal Data Protection Law
Remote Video Hearings Roll-out — Makkah Region Regulatory 9 Medium SAR 900K Eng. Yasser M. Al-Zahrani Eng. Yasser M. Al-Zahrani Director, Cybersecurity P-026 · y.alzahrani@bog.gov.sa Mitigate Open In 95 days 2027-01-31 · 23 Shaʻban 1448 AH 10 d RSK-0004
Cloud hosting capacity exceeded at launch
Mueen Digital Platform — Release 4 Technical 8 Medium SAR 900K Eng. Omar H. Bawazir Eng. Omar H. Bawazir Director, IT Infrastructure P-024 · o.bawazir@bog.gov.sa Mitigate In progress In 48 days 2026-12-15 · 6 Rajab 1448 AH 9 d RSK-0008
Late delivery of identity & access management licences
Mueen Digital Platform — Release 4 Contractual 6 Low SAR 450K Khalid N. Al-Mutairi Khalid N. Al-Mutairi Senior Finance & Contracts Specialist P-007 · k.almutairi@bog.gov.sa Transfer Open In 33 days 2026-11-30 · 20 Jumada II 1448 AH 10 d RSK-0011
Updated user-experience standards from the Digital Government Authority
Mueen Digital Platform — Release 4 Regulatory 6 Low SAR 280K Lama S. Al-Harbi Lama S. Al-Harbi Senior Business Analyst — Judicial Procedures P-006 · l.alharbi@bog.gov.sa Accept Open In 95 days 2027-01-31 · 23 Shaʻban 1448 AH 16 d RSK-0045
Preliminary-handover snags on the fire and alarm systems
Abha Administrative Court Rehabilitation Technical 6 Low SAR 600K Eng. Waleed O. Al-Juhani Eng. Waleed O. Al-Juhani Director, Facilities Operations & Maintenance P-021 · w.aljuhani@bog.gov.sa Mitigate Open In 15 days 2026-11-12 · 2 Jumada II 1448 AH 2 d