Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-032On track11Benefits RealizationAgile

HR Self-Service

Add to watchlist

Employee self-service for 34 HR procedures, from leave to secondments, linked to the Masar platform.

Budget (BAC)

SAR 11.4M

Actual cost

SAR 10.8M

⁦94%⁩ of budget

Progress

⁦100%⁩

Planned ⁦100%⁩

Estimate at completion

SAR 10.8M

SPI · CPI

1.00Schedule performance index · 1.001.06Cost performance index · 1.06

Forecast finish

⁦2025-09-21⁩

On baseline

Benefits RealizationPhase ⁦11⁩ of ⁦11⁩

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate17 November 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate31 May 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate15 June 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate26 July 2024Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionConditional goDate20 July 2025Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate20 August 2025Handover · CompleteHandover · Complete
  10. Gate into «Closure»DecisionConditional goDate30 September 2025Closure · CompleteClosure · Complete
  11. Gate into «Benefits Realization»DecisionGoDate29 November 2025Benefits Realization · Current phaseBenefits Realization · Current phase

Board of Grievances

Project charter

HR Self-Service

APPROVEDV2Approved ⁦2024-05-03⁩

1Project identity

Project name
HR Self-Service
Project code
PRJ-2026-032
Sponsor
Sarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.sa
Project manager
Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa
Business owner
Abdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@bog.gov.sa
Portfolio & programme
Technology & Enterprise Systems PortfolioEnterprise Systems & Archiving Programme
Type & methodology
IT · Agile
Current phase
11Benefits Realization

2Background & rationale

Employee self-service for ⁦34⁩ HR procedures, from leave to secondments, linked to the Masar platform.

3Objectives

  1. 1Develop judicial and administrative talent
  2. 2Improve financial planning and diversify revenue

4Scope

In scope

  • Employee self-service for ⁦34⁩ HR procedures, from leave to secondments, linked to the Masar platform.
  • Migration from legacy systems
  • ERP integration

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

  1. 1Migration from legacy systems
  2. 2ERP integration
  3. 3Essential cybersecurity controls

6Deliverables

1Project management plan⁦2024-05-26⁩
2Main deliverable — stage 1⁦2025-01-22⁩
3Main deliverable — final stage⁦2025-07-20⁩
4Final report⁦2025-09-30⁩

7Key milestones

  1. Charter approved⁦2024-05-03⁩
  2. Contract signed⁦2024-07-26⁩
  3. 50% of works complete⁦2025-01-22⁩
  4. Provisional acceptance⁦2025-08-20⁩
  5. Closure⁦2025-09-30⁩

8Budget

  • Main contract⁦71.9%⁩8.2M
  • Supervision & consulting⁦14.0%⁩1.6M
  • Internal team⁦8.8%⁩1M
  • Contingency reserve (⁦5%⁩)⁦5.3%⁩600K
The owning sector’s approved budgetTotal11.4M

9Timeline

Start
2024-05-0526 Shawwal 1445 AH
Baseline finish
2025-09-308 Rabiʻ II 1447 AH
Duration
⁦17⁩ months

10Key risks

  • No risks recorded yet.

11Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

  • Named internal staff available throughout
  • Approvals land within workflow SLAs

13Stakeholders

  • Project sponsorDecisions and funding
  • Business ownerAccepts deliverables, owns benefits
  • Projects Follow-up Office (EPMO)Governance and compliance

14Success criteria

  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • EPMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, issues, weekly statusWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Board
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close