Original
Original baseline
- Finish
- 2025-09-30
- Budget
- SAR 11.4M
- 16 activities
Approved with the project plan at the planning gate.
Approved 2024-05-05 · by Sarah A. Al-Qarni
Employee self-service for 34 HR procedures, from leave to secondments, linked to the Masar platform.
Budget (BAC)
Actual cost
94% of budget
Progress
Planned 100%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
Benefits RealizationPhase 11 of 11
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2024-05-05 · by Sarah A. Al-Qarni
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Dana S. Al-Saleh
What changed from version A to version B
Finish
2025-09-302025-09-21
−9 days
Budget
SAR 11.4MSAR 11.4M
0.00 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference