PRJ-2026-032On track11Benefits RealizationAgile

HR Self-Service

Add to watchlist

Employee self-service for 34 HR procedures, from leave to secondments, linked to the Masar platform.

Budget (BAC)

SAR 11.4M

Actual cost

SAR 10.8M

⁦94%⁩ of budget

Progress

⁦100%⁩

Planned ⁦100%⁩

Estimate at completion

SAR 10.8M

SPI · CPI

1.00Schedule performance index · 1.001.06Cost performance index · 1.06

Forecast finish

⁦2025-09-21⁩

On baseline

Benefits RealizationPhase ⁦11⁩ of ⁦11⁩

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate17 November 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate31 May 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate15 June 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate26 July 2024Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionConditional goDate20 July 2025Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate20 August 2025Handover · CompleteHandover · Complete
  10. Gate into «Closure»DecisionConditional goDate30 September 2025Closure · CompleteClosure · Complete
  11. Gate into «Benefits Realization»DecisionGoDate29 November 2025Benefits Realization · Current phaseBenefits Realization · Current phase

Scope statement

What the project delivers, what it does not, and when a deliverable counts as accepted.

Employee self-service for ⁦34⁩ HR procedures, from leave to secondments, linked to the Masar platform.

In scope

  • Employee self-service for ⁦34⁩ HR procedures, from leave to secondments, linked to the Masar platform.
  • Migration from legacy systems
  • ERP integration

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

Acceptance criteria

  • Main deliverable — stage 1Meets the approved specification, signed off by the business owner
  • Main deliverable — final stageMeets the approved specification, signed off by the business owner

Scope baseline

Every approved change creates a new baseline

  1. 1

    SB-1Current⁦2024-05-28⁩

    Baseline approved at the planning gate

    Budget11.4MFinish⁦2025-09-30⁩

Requirements register

⁦6⁩ requirements of five kinds, with the trace status of each

By type

  • Business1
  • Functional1
  • Technical2
  • Regulatory1
  • Security1

Fully traced

⁦100%⁩

6/6 · linked to a deliverable, task and test

Test passed

⁦100%⁩

6/6 · test result is a pass

Accepted

⁦100%⁩

6/6 · signed off by the business owner

⁦6⁩ results
Export CSV
REQ-032-01One system for the proceduresBusinessMustCompletedAbdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@bog.gov.saSB-1
REQ-032-02Historical data migrationTechnicalMustCompletedDana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.saSB-1
REQ-032-03Ready operational reportsFunctionalMustCompletedAbdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@bog.gov.saSB-1
REQ-032-04ERP integrationTechnicalCouldCompletedDana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.saSB-1
REQ-032-05Data classificationRegulatoryCouldCompletedAbdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@bog.gov.saSB-1
REQ-032-06Identity and access managementSecurityShouldCompletedDana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.saSB-1
⁦1⁩–⁦6⁩ of ⁦6⁩

Traceability matrix

Requirement → deliverable → task → test → acceptance. No requirement has a gap.